This is an archive article published on March 22, 2024
1 worker dead, 8 injured as under-construction bridge in Bihar collapses
Three slabs of a 10.5 km-long bridge over the Kosi River in Bihar’s Supaul collapsed on Friday morning. Efforts are on to ascertain if any more workers are trapped in the debris.
Written by Santosh Singh
New Delhi | Updated: March 22, 2024 11:10 AM IST
2 min read
Whatsapp
twitter
Facebook
Reddit
The 10.5 km-long bridge over the Kosi River connecting Bakour in Supaul and Bheja in Madhubani is being built at a cost of over Rs 1,200 crore. (Credit: Sanjay Soni)
A labourer was killed and eight others were injured after three slabs of an under-construction bridge in Bihar’s Supaul collapsed on Friday morning. Rescue operations are currently underway and efforts are on to ascertain if any more workers are trapped in the debris, officials said.
The 10.5 km-long bridge over the Kosi River connecting Bakour in Supaul and Bheja in Madhubani is being built at a cost of over Rs 1,200 crore. Though the foundation stone for the project was laid in 2014, the bridge is yet to be completed.
VIDEO | Several workers are reportedly trapped as a part of an under-construction bridge over #Kosi River collapses in Bihar’s #Supaul. Rescue work underway. More details are awaited.#BiharNews
The incident took place at around 7 am. Three slabs from pillar numbers 152, 153 and 154 collapsed. “Rescue and relief work is underway to find out if more workers are trapped inside the debris,” Supaul District Magistrate Kaushal Kumar said.
A part of the Centre’s ambitious Bharatmala Project, the Supaul bridge is a joint venture between Gammon Engineers and Contractors Private Limited and Transrail Lighting Limited. The project was awarded by Bihar Rajya Pul Nirman Nigam Ltd and Transrail Lighting Limited is in charge of the construction.
Story continues below this ad
Last year, in June, a 200-metre stretch of the upcoming Aguani (Khagaria)-Sultanganj (Bhagalpur) bridge over the Ganga River had caved in after three pillars supporting it collapsed. No casualties were reported. The 3.1-km bridge being built at a cost of Rs 1,710 crore was scheduled to be completed in 2019 and had received four extensions.
In April 2022, the superstructure of an under-construction four-lane bridge over the Ganga River linking Sultanganj (Bhagalpur) and Khagaria collapsed. No casualties were reported in the incident. This was one of the biggest bridges being built over the Ganga River.
Santosh Singh is a Senior Assistant Editor with The Indian Express since June 2008. He covers Bihar with main focus on politics, society and governance. Investigative and explanatory stories are also his forte. Singh has 25 years of experience in print journalism covering Bihar, Delhi, Madhya Pradesh and Karnataka.
... Read More