Goregaon Mulund Link Road

GOREGAON MULUND LINK ROAD NEWS

54 containers carrying parts for Goregaon Mulund Link Road arrive from Japan

July 19, 2025 9:03 pm

According to officials, the remaining parts of the TBM machine are expected to arrive by August 15.

Goregaon Mulund Link Road: BMC approves realignment of 6.5-km twin tunnels

December 07, 2024 8:44 pm

Under earlier plan, tunnels passed below farmlands of tribal communities inside SGNP.

Decades-old temple in Dindoshi razed to make way for Goregaon Mulund Link Road Project

October 19, 2024 12:01 pm

The demolition drive was undertaken smoothly with no resistance from the temple authorities.

Adhere to dust mitigation norms’: BMC issues notice to 97 builders

November 05, 2023 5:44 pm

The civic body has also issued another notice to the contractor carrying out the Goregaon Mulund Link Road (GMLR) project in the western suburbs.

Goregaon-Mulund link road tunnel work to start in October, a year after tender floated

August 06, 2023 2:22 pm

While the twin tunnels will be 4.7 km long, the overall length of the link road will be around 12.2 km.

BMC gets three bids for construction of underground tunnels in GMLR project

July 16, 2023 2:12 pm

The civic body failed to receive any bids from eligible contractors till June 30 and the deadline for submitting the bids was postponed four times.

Explained: How will Mumbai's Goregaon-Mulund link project benefit commuters?

April 18, 2022 11:49 am

The Goregaon-Mulund Link Road is an elevated road being constructed to connect Goregaon in the western suburbs to Mulund in the eastern suburbs. A look at the project and its cost, and the status of work.

Aaditya performs GMLR flyover’s ground-breaking ceremony

March 13, 2022 8:46 am

“Honoured to have done the bhumi poojan of an important promise of the Shivsena, the Goregaon-Mulund Link Road. This road will be a game-changer for Mumbai’s traffic woes, especially on the east-west connectivity front,” Thackeray tweeted.

Goregaon-Mulund link road: Construction of tunnel to begin by 2016-end

January 15, 2016 12:51 pm

The firm, Pedico, has been contracted at a cost of Rs 2.3 crore to design and plan the 6-km tunnel which will be the first such underground road in the city.

Goregaon Mulund Link Road: Consultant to review project, realign route

October 03, 2015 5:08 am

Once the alignment is finalised by January 2016, BMC will undertake a tendering process to execute the project.