BMC gets three bids for construction of underground tunnels in GMLR project

The civic body failed to receive any bids from eligible contractors till June 30 and the deadline for submitting the bids was postponed four times.

Mumbai GMLRThe GMLR project is being divided into four phases and at present the first and second phase is on, which includes construction of flyovers, traffic interchanges, widening of existing roads and creating traffic interchanges. (Representational image)
Written by: Pratip Acharya
3 min readMumbaiJul 16, 2023 02:12 PM IST First published on: Jul 9, 2023 at 08:19 PM IST

Nearly eight months after floating tenders for construction of two underground tunnels which will be part of Brihanmumbai Municipal Corporation’s ambitious Goregaon Mulund Link Road (GMLR) project, the civic body has so far received three bids.

In a bid to ease traffic, the BMC is creating the 12.2 km-long GMLR, which will connect Goregaon in the western suburbs with Mulund in the eastern suburbs through a serious of arterial roads, underground tunnels and bridges.

Advertisement

The tender for constructing the underground tunnels was floated in October 2022. However, the civic body failed to receive any bids from eligible contractors till June 30 and the deadline for submitting the bids was postponed four times. According to civic officials, the three firms who have submitted their final bids are NCC Limited, Larsen and Toubro and Afcons Infrastructure Limited. The cost of the twin tunnels has been pegged at Rs 6,300 crore while the overall project has been pegged above Rs 8,550 crore.

Pratip Acharya is a seasoned journalist based in Mumbai reporting for The Indian Express Read More