For the upcoming five years starting April 2014, the power regulator CERC is currently in the process of reviewing the existing tariff norms for both generation and transmission projects in the country.
Two areas that could merit changes are the normative debt-equity ratio for new projects and the treatment of equity after the debt is paid off.
Tweaking the norm to a more reasonable 75:25 or an 80:20 ratio for future projects is also pertinent, considering that the scale of project funding has gone up several times over the years, with most mega hydro projects and thermal ultra mega power projects entailing financing of well over Rs 20,000 crore. International experience too bears this out, with countries such as the US following a 90:10 normative D:E ratio for power projects. Keeping in view the widening of the debt market, better due diligence at banks to decide on serious promoters and the increased ability of developers to raise bonds, there might be a compelling case to revisit the existing approach.
With regard to the servicing of equity post debt repayment, the existing approach is to continue to service the entire equity to the tune of 30 per cent, even though the equity is being repaid to the developer through the depreciation route under what is known as the ‘liability side’ approach.
Paying returns on portion of equity that has been returned via depreciation route (assets already being written off up to 10 per cent salvage value), simply increases the tariff. This treatment of equity, which has been enshrined in the tariff policy 2006, and is being happily followed by the regulators, is tantamount to double-charging the consumers. Its impact is more pronounced in distribution sector where the capex is continuous as the new equity is added to the non-existent normative equity, resulting in an inflated ROE and hence higher consumer tariff.