Premium
This is an archive article published on May 17, 1998

7 MNCs in race for EPC deal for AES project

BHUBANESWAR, May 16: American utility major AES Transpower has shortlisted seven multinational giants/consortia for the EPC engineering, pr...

.

BHUBANESWAR, May 16: American utility major AES Transpower has shortlisted seven multinational giants/consortia for the EPC engineering, procurement and construction job for its Ib Valley thermal project through fresh international competitive bidding.

The companies and consortia selected through pre-qualification bidding are Raytheon, Black amp; Veatch, Duke-Flour Daniel-Tata, Lamp;T and Sargent Lundy, Bechtel-Foster Wheeler-Mitsubishi Heavy Industry-Nichiman, ABB and Siemens.

quot;The selected companies/consortia are currently conducting site visits and we expect that a party for the EPC job would be selected within the next 10 weeks,quot; a senior AES official said.

AES, in fact, had to speed up the process of selecting an EPC contractor as the Central Electricity Authority CEA insisted on the final price of the EPC job. AES had submitted a ceiling price when it had approached the CEA for techno-economic clearance for the project. However, after sitting over the file for over a year and half, the CEA told AESin March 1998 the ceiling price was not acceptable to the authority and directed AES to furnish the final price after the competitive biddings.

The AES official said the pre-bid meeting would be held in the first week of June and by the end of July the bidding would be finalised. He said the CEA would scrutinise the EPC bidding and, if required, negotiate the price with the successful bidder before giving clearance. CEA has cleared the 2215;250 mw coal fired project as far as technical parameters are concerned.

Earlier, AES had selected a Raytheon-led consortium of GE, Foster Wheeler and Lamp;T for the EPC job through a global competitive bidding in 1993. The consortium was also paid some amount for preliminary work for the original 2215;210 mw thermal project. AES had to renege on the contract as it went for a changed configuration of 2215;250 mw instead of 2215;210 mw.

Meanwhile, AES has initiated the process of acquiring the required 650 acre of land, including the ash pond for the project. It will take over siteV and site VI of state-owned Orissa Power Generation Corporation8217;s Ib Valley project. OPGC has developed a total of 1,800 acre of land in the coal mine rich area of Ib Valley in Jharsuguda district to set up six units of thermal power stations. The state generating company has already set up two units of 210 mw each at site I amp; site II and is in the process of setting up two more units of the same capacity in the adjacent site III and site IV.

Story continues below this ad

The AES official said the company is likely to go in for financial closure by the end of December.

 

Latest Comment
Post Comment
Read Comments
Advertisement
Advertisement
Advertisement
Advertisement