Premium
This is an archive article published on August 30, 2023

All you need to know about the Mizoram bridge that collapsed, killing 23

The bridge is one of 185 bridges part of the 51.38 km long Bairabi-Sairang railway project. The piers — or columns — of the bridge had been erected at the time of the incident, which took place while one of the steel girders was being launched.

Mizoram Bridge CollapseThe bridge — being constructed over an undulating hilly forested terrain and a river — is part of a long in-the-works project to take railway connectivity to Aizawl, the state capital. (Express photo)
Listen to this article
All you need to know about the Mizoram bridge that collapsed, killing 23
x
00:00
1x 1.5x 1.8x

When a steel girder for an under-construction railway bridge in Mizoram collapsed earlier this week, killing 23 people working on it, they were at a dizzying height of around 100 metres above ground. The deceased belonged to Malda in West Bengal. Three other workers were injured in the accident.

The bridge — being constructed over an undulating hilly forested terrain and a river — is part of a long in-the-works project to take railway connectivity to Aizawl, the state capital. The site of collapse was in Sairang, around 19 km from Aizawl, and the bridge is on the approach to Sairang station, the last point of this broad gauge railway project.

The bridge is one of 185 bridges part of the 51.38 km long Bairabi-Sairang railway project. The piers — or columns — of the bridge had been erected at the time of the incident, which took place while one of the steel girders was being launched. The work was being carried out as a joint venture between ABCI Infrastructures Private Limited and BBJ Construction Company Limited, a Government of India enterprise, both based in Kolkata.

Story continues below this ad

According to Sabyasachi De, Chief Public Relations Officer at North East Frontier Railway, the cause of the collapse is currently being investigated by a four-member committee constituted by the Ministry of Railways. A press release from the North East Frontier Railway announcing the completion of this pier earlier this year had stated that the pier was one of the “most critical parts of the project”, since it is in the middle of the river Kurung and the foundation had been built in the running stream.

Mizoram bridge collapse The Mizoram bridge collapse

This prevalence of tunnels and bridges is typical of railway lines in Himalayan regions, explained De. “These railway lines can’t be made along the surface and the reason that a bridge that high is required is that we need to maintain a certain gradient in a railway line. Our limitation is that our gradient is fixed, and all railway lines anywhere in the world are built in a fixed gradient. In order to maintain that, all these kinds of infrastructure are necessitated. In hilly terrain, if we need to cross a low valley, then naturally a tall bridge will be required,” he said.

However, these massive structures in the hill state’s terrain are being viewed with some concern by observers. “The pillars for this railway track are being erected very high in this terrain. Here, the topography is very rugged. In terms of geology, the terrain is very unsaturated. This means the soil is soft and swells very easily because of rainfall, making it not very stable,” said Jimmy Lalnunmawia, the head of geology department at Mizoram University.

The project has been in the making for more than a decade now. However, officials said the August 23 incident is unlikely to lead to an extension in the timeline since the substructure was not damaged. The current deadline for its completion as per the Indian Railways is March 2024.

Story continues below this ad

The proposal for land acquisition was submitted to the state government in 2011. The land was handed over to the Railways by early 2014 and the foundation stone laid down later that year. The Railways has cited a number of factors that slowed down the project, including long and intense monsoon; frequent landslides along access roads that stopped the movement of workers and material; the need to bring in materials from other states; the absence of local labour for heavy construction work; the shortage of workers elsewhere willing to work in the state’s hilly terrain; and COVID-19.

Latest Comment
Post Comment
Read Comments
Advertisement
Advertisement
Advertisement
Advertisement