While one lane of Thane Creek Bridge-3 is likely to be open in April, the MSRDC is gearing up to complete construction of all six lanes by October end.
The ongoing construction of Thane Creek Bridge-3 is designed to accommodate the increasing vehicular traffic expected once the Navi Mumbai International Airport becomes operational. This project involves expanding the current Thane Creek Bridge-2 to add six more lanes. With significant progress achieved on the South Mumbai to Vashi carriage – comprising over 85 per cent of the project – the Maharashtra State Road Development Corporation (MSRDC) is hoping to open one side of the road, potentially by April 2024.
Alignment:
1.8 km-long bridge built over Thane Creek, parallel to the existing Thane Creek Bridge 2, comprising 3 plus 3 lanes each (total six lanes)
Benefits:
Challenges:
Cost: Rs 775 crore
Progress: 68% of overall project work done
What officials say:
“Our target is to finish the construction of Thane Creek Bridge 3 by the end of October, and following its completion, the bridge will be accessible to traffic. The one-side road from Mumbai to Vashi on TCB-3 is already prepared and is expected to be finished by April. Consequently, we intend to open this one-side road. To facilitate efficient traffic flow, toll lanes have been strategically implemented on this road,” Nitin Borule, MSRDC executive engineer, said.