Stay updated with the latest - Click here to follow us on Instagram

The Brihanmumbai Municipal Corporation (BMC) completed the 1-km tunnel boring for the coastal road project late Saturday night.
Officials from the coastal road department said that by next January the work on the tunnel for south-bound traffic will be completed.
On January 11, Chief Minister Uddhav Thackeray launched India’s biggest Tunnel Boring Machine (TBM) ‘Mavala’ with diameter of 12.15 metres. The BMC had set a target to complete both tunnel works in 20 months, but the pace of work was impacted due to the pandemic.
“The work of the south-bound tunnel will be completed by January as only 1-km work is remaining. Due to Covid-19 there was delay of at least two to three months this year. The TBM will make a breakthrough at Girgaon Chowpatty and from there it will be brought back to Priyadarshini Park for boring of another tunnel for north-bound traffic,” said Vijay Nighote, chief engineer, coastal road department.
State Environment Minister Aaditya Thackeray has also tweeted about Mavala completing 1-km tunnel work.
The BMC has so far completed over 40 per cent work for the Rs 12,721-crore project. Reclamation work in the sea has been completed up to 91 per cent, and about 9 hectares remain out of 111 hectares. “The remaining reclamation will take a couple of months as we don’t require it immediately. This reclamation will be done at Haji Ali side and Worli near the sea link at a later stage,” said an official.
Meanwhile, the BMC is yet to begin a survey for compensation of fishermen affected by the reclamation work. Officials said that after they failed to get a response from any contractor for the fishermen survey, they have written to Tata Institute of Social Sciences (TISS) seeking help for the survey.
Stay updated with the latest - Click here to follow us on Instagram