Premium
This is an archive article published on November 30, 2010

Tracking the Monorail

The first phase of the monorail corridor from Chembur to Wadala would be commissioned by April next year,according to the Mumbai Metropolitan Region Development Authority.

The first phase of the monorail corridor from Chembur to Wadala would be commissioned by April next year,according to the Mumbai Metropolitan Region Development Authority (MMRDA).

When it opens,the corridor is likely to have two stations less than the number planned. MMRDA Joint Metropolitan Commissioner Ashwini Bhide said,”The project would be commissioned by April,but it would be without two stations on the corridor. One would be the V N Purav or the RC Marg junction and second would be the Fertilizer Colony station. There were some issues with the alignment of the Purav Marg and this delayed the work. But we would try to finish the Fertilizer Colony station before April. It is not unusual to commission the corridor even if a station is constructed after commissioning of the service. It won’t hamper the monorail functioning.”

The Rs 2,460-crore corridor from Jacob Circle to Chembur via Wadala was to come up in two phases. The first phase from Wadala to Chembur,a stretch of 8.26 kilometres,was to be commissioned by December 2010 and the remaining 11.28 kilometres by April 2011.

A visit to the site,from Wadala to Chembur,would show that the April deadline seems unlikely to be met. The Wadala depot,where rakes will be maintained and where the control room for the monorail is to come up,is far from completion. The construction depot was supposed to be completed by June and thereafter,six monorail rakes were to be brought for the first corridor.

The MMRDA’s plan to commission the corridor with even four stations seems a tall order. Work on the Bhakti Park station,the first on the corridor,at Wadala has begun,but work at other stations like Chembur,the last on the corridor,have not yet begun. On some stretches on RC Marg which cover a sizeable portion of the corridor,work of erecting piers has not commenced. “We have been given the deadline of completing the work by May 2011,” said Bhide.

The MMRDA has also not yet got permission from the High Court to start work on the stretch where there is a patch of mangroves near Wadala. “Only three piers would be constructed on that stretch and this should not take time. Our alignment had been fixed before the patch was declared a mangrove forest,we have approached the High Court and getting the permission would not be a problem,” added Bhide.

Stay updated with the latest - Click here to follow us on Instagram

Latest Comment
Post Comment
Read Comments
Advertisement
Loading Taboola...
Advertisement