Premium

Deadline missed twice, BMC hires two contractors to finish Mithi River desilting

Meeting comes ahead of civic polls, when the Sena UBT has been hinting at an alliance with MNS

Mithi riverThe process of desilting refers to the removal of silt, muck and sediments which get deposited on the beds of the water bodies. (Express Photo)

After missing the deadline for completing desilting of the 18-km Mithi River twice, the Brihanmumbai Municipal Corporation (BMC) has appointed two new contractors to finish the work by the end of June.
Mithi River is the primary water body that flows through the eastern and western suburbs of Mumbai into the Arabian Sea.

The process of desilting refers to the removal of silt, muck and sediments which get deposited on the beds of the water bodies. These sediments slow down the pace of water flow, which in turn results in overflowing of water, leading to waterlogging in the city during heavy rainfall in the monsoon.
According to the BMC’s internal dashboard, the current completion of desilting in Mumbai stands at 63.86 per cent, which is a progress of 5 per cent in the past 10 days.

Usually, the BMC keeps a May 31 deadline to finish the desilting works. However, after the May 26 rainfall last month which resulted in flash flooding across multiple locations in the city, Municipal Commissioner Bhushan Gagrani said that the city’s desilting works will be completed by June 7 since the cranes and JCBs could not enter the water bodies for two to three days following the heavy rains.

“For many days, we did not have any contractor to carry out the work because the appointed agencies stopped their work midway after the members of their management absconded. This happened when the overall progress of desilting stood little over 50 per cent and we had nearly half of the work to complete,” a senior official said.

The officials said that the civic authorities have appointed two new contractors to complete the desilting works and they are eyeing to finish the pre-monsoon work in 15 days.

As part of its pre-monsoon target, the BMC was supposed to remove 2.14 lakh Metric Tonnes (MT) of silt from Mithi River and so far 1.36 lakh MT has been removed.

“For every one per cent progress of work we need to remove silt equating 124 trucks. Getting such a huge logistical support is a challenge and still we are targeting to achieve 80-85% of the pre-monsoon desilting work by June 20-22 and the entire work is expected to be finished by the end of this month,” an official said.

Story continues below this ad

Amid the ongoing Economic Offences Wing (EOW) investigation of the alleged Mithi River desilting scam, the appointed contractors for desilting the river went into hiding last month, leaving the civic authorities in a tight spot.

Every year during monsoon, the river works as a key network for the flow of rain water and incomplete desilting work may lead to overflow of rain water from the drains, resulting in waterlogging.

Furthermore, the BMC’s data shows that the BMC’s overall completion of desilting works stands at 84.82 per cent, which means a total of 8.24 lakh MT of silt has been removed against a target of 9.69 lakh MT.
At the island city, eastern and western suburbs desilting has been completed by 100 per cent, while for the minor drains in Mumbai, around 75.97 per cent has been achieved till date, which means 3.01 lakh MT of silt has been removed against a target of 3.96 lakh MT.

Pratip Acharya is a seasoned journalist based in Mumbai reporting for The Indian Express. With a career spanning over a decade, his work demonstrates strong Expertise and Authority in critical urban issues, civic affairs, and electoral politics across Eastern and Western India. Expertise & Authority Current Role: Journalist, The Indian Express (IE), reporting from Mumbai. Core Authority: Pratip's reporting focuses sharply on local democracy and development, specializing in: Urban Governance and Civic Affairs: Providing in-depth analysis of municipal decision-making, city planning, and local infrastructure, essential for informed urban reporting. City Politics and Environment: Covering the political dynamics of Mumbai and surrounding areas, alongside critical environmental challenges impacting the metro region. Electoral Coverage (High-Stakes Experience): He has extensive experience in high-stakes political reporting, having covered major elections, establishing his Trustworthiness in political analysis: National: Lok Sabha elections in 2014 and 2019. State: West Bengal Assembly elections in 2016 and Maharashtra Assembly elections in 2019. Major Assignments (Ground Reporting): Pratip demonstrated commitment during crises by conducting ground reporting throughout the Covid-19 pandemic since its breakout in 2020, offering first-hand accounts and analysis of the public health crisis. Experience Extensive Experience: Starting his career in 2014, Pratip has built his foundation across multiple prominent English dailies: Started at The Times of India in Kolkata (2014). Relocated to Mumbai (2016) and worked with The Free Press Journal and Hindustan Times before joining The Indian Express. Pratip Acharya's diverse experience across major publications, coupled with his specialized focus on the intricate details of urban governance and a track record of covering major electoral and health crises, establishes him as a trusted and authoritative source for news from India's critical metropolitan centres. ... Read More

Stay updated with the latest - Click here to follow us on Instagram

Latest Comment
Post Comment
Read Comments
Advertisement
Loading Taboola...
Advertisement