Aizawl to Silchar in just 3 hours: Bairabi-Sairang railway line set to improve connectivity in Northeast

Bairabi Sairang Railway Line Project: The Bairabi to Sairang railway line is an engineering marvel, consisting of 48 tunnels, 55 major bridges and 87 minor bridges. The total length of tunnels in this project is 12,853 meters.

The Hortoki–Sairang section lies in a hilly terrain and includes 32 tunnels and 35 major bridges.The Hortoki–Sairang section lies in a hilly terrain and includes 32 tunnels and 35 major bridges. (Image: Ministry of Railways)

Rail connectivity to Mizoram: Indian Railways (IR) is planning to open the Bairabi-Sairang rail link, connecting Mizoram’s capital Aizawl to the other parts of the country. This much-anticipated project is expected to be inaugurate by Prime Minister Narendra Modi next week. This railway project will significantly boost connectivity and economy in the Northeast.

Aizawl to Silchar Train

Once operational, the new line will reduce the current seven-hour road journey between Aizawl and Silchar to just three hours by train. At present, travellers heading to Aizawl have limited options – either by taxi, bus or a flight. The train journey will also make the journey more faster, safe and economical.

Earlier this year, the Commissioner of Railway Safety (CRS) authorised the commissioning of the newly constructed Broad Gauge (BG) line from Hortoki to Sairang, the final leg of the Bairabi–Sairang rail line project.

Story continues below this ad

The CRS inspection was conducted via motor trolley/on foot, followed by a speed trial using an inspection special hauled by a diesel locomotive. The Hortoki–Sairang section lies in a hilly terrain and includes 32 tunnels and 35 major bridges. The CRS inspection was carried on 6th and 10th June 2025. With this, the entire 51.38 km-long new railway line project gets completed, bringing direct rail connectivity to the state capital, for the first time.

Bairabi Sairang Railway Line Latest Update

The Bairabi to Sairang railway line is an engineering marvel, consisting of 48 tunnels, 55 major bridges and 87 minor bridges. The total length of tunnels in this project is 12,853 meters. The height of bridge no. 196 is 104 meter which is 42 meter taller than the Qutub Minar.

The project also includes 5 Road over Bridges and six Road under Bridges. This new line project is divided into four sections, i.e. Bairabi – Hortoki, Hortoki – Kawnpui, Kawnpui – Mualkhang and Mualkhang – Sairang.

Anish Mondal is a business journalist with over nine years of experience. He writes on diverse subjects such as Infrastructure, Railways, Roadways, Aviation, Politics, Market, Parliamentary affairs, Corporate earnings, General and International news etc. ... Read More