April 23, 2025 12:58 am
Gosikhurd Irrigation Project was approved in March 1983 to create irrigation potential in 2,50,800 hectares annually in Bhandara, Nagpur and Chandrapur districts
October 23, 2024 5:49 pm
From land acquisition to pending railway crossing work, a range of issues are plaguing the Gosikhurd National Irrigation Project in Maharashtra’s Vidarbha region.
March 11, 2023 2:32 pm
The project coming up in Maharashtra’s Vidarbha region has been in limbo for the past 39 years. The state allocated Rs 1,500 crore in this year’s Budget, but the total fund required is Rs 4,500 crore.
March 20, 2022 8:49 am
The project needs Rs 4,249 crore to be completed. The total project cost is now at Rs 18,500 crore but officials warned it may rise to Rs 20,000 crore.
March 12, 2021 11:16 pm
The state’s second-largest dam project, which was given the national status in 2009, is still facing financial ordeal even after 37 years.
January 27, 2021 10:34 pm
The Centre has also agreed to allocate Rs 5,000 crore to complete the project which has the potential to irrigate 2.5 lakh hectares of land
September 13, 2020 12:38 pm
The irrigation department’s request for higher allocation of funds for the project has not been accepted. In the two-day monsoon session, supplementary demands failed to accommodate the financial demand for the project.
November 10, 2018 3:15 am
"If we reflect on the progress made in the last four years, it is very satisfactory. The irrigation potential in Gosikhurd has increased from 8,449 lakh hectares in 2013-14 to 47,557 lakh hectares in 2017-18,” the CM said.
April 16, 2014 4:15 pm
Even as Chief Minister Prithviraj Chavan is being lauded for his efforts resulting in the Centre releasing Rs 405 crore for the Gosikhurd Irrigation Project,it seems this amount would not help the stalled three-decade-old project even stumble back on its feet.
April 17, 2014 2:25 pm
CM Prithviraj Chavan is knocking at the Centre door for funds to complete the Gosikhurd irrigation project in Vidarbha.