Premium
This is an archive article published on April 14, 2005

After George clean chit, a UPA U-turn

Desperate to regain lost ground after it gave a clean chit to George Fernandes on purchases made during the Kargil war, the Centre today fil...

.

Desperate to regain lost ground after it gave a clean chit to George Fernandes on purchases made during the Kargil war, the Centre today filed an additional affidavit before the Supreme Court saying the CBI was probing some of these deals and action would be taken against the former Defence minister if his connivance was established in any of them.

The CBI will be asked to probe another 23 cases of which 20 are yet to be vetted by the CAG, the affidavit said.

“The Government is committed to take strict action against officers/ authorities, including the former Defence Minister, if it is found that the excuse of Kargil was taken to make purchases with a motive of personal benefit in violation of rules and regulations,’’ said the affidavit filed by R Chaturvedi, Under-Secretary, Ministry of Defence.

Story continues below this ad

Chaturvedi stated that he was filing the the present affidavit as it was pointed out that an earlier counter-affidavit filed in March by the MoD in a PIL, which asked the Centre to explain action taken on the CAG report on alleged irregularities in the 1999 Kargil war purchases, “appeared to be evasive and was not complete in all respects.”

Subsequently, the April 5 affidavit had justified Defence purchases made during Operation Vijay, including changes made to arms procurement policy and continued acquisitions made under the relaxed norms even after end of hostilities. This, it said, “in no way violated any of the financial rules of the Government or the Defence Procurement Procedure, 1992.”

But the affidavit left the UPA red-faced, particularly because the Congress had been at the forefront of an intense agitation against Fernandes on the issue, both inside and outside Parliament, during the NDA tenure.

Today’s affidavit was a virtual U-turn from the earlier one and relied heavily on the CAG report which, it said, had “concluded that the excuse of Kargil was cited to push through procurements that would otherwise have been scrutinised more closely.”

Story continues below this ad

The Government, so far, had scrutinised five transactions—hand-held thermal imagers, terminally guided munitions (Krasnapol), ammunition for T-72 tanks, ammunition and aluminium caskets—‘‘to fix responsibility…on the basis of the findings of the CAG’’, the additional affidavit said.

The other purchases that the CBI would be asked to look into include: illuminating ammunition for 155 mm guns (Rs 52.47 crore), special ammunition for 40 mm L-70 gun (Rs 166.44 crore), automatic grenade launchers (Rs 52.13 crores), spares for 155 mm guns (Rs. 97.65 crore), special clothing and mountaineering equipment (Rs 95.15 crore) and 155 mm red phosphorus ammunition (Rs 55.1 crore).

While the first two deals, which also figure in the Tehelka tapes, have been referred to the CBI for further probe, the rest are also being transferred to the agency, it said.

The affidavit submitted that the Government was also exploring whether the facts reveal a prima-facie case of commission of criminal offences under law given that CAG had pegged the financial loss at over Rs 2000 crores, “in addition to the fact that the equipments did not materialise at the time of its need.”

Story continues below this ad
TURNAROUND TIME

Incidentally, the Government had stated in the earlier affidavit that the modified norms had not violated any financial rules of the government.

The April 5 affidavit had also explained the delay in the supply of arms thus: “At the time of making projections, the duration of operations, the nature and levels of conflict and the possibility of spread of the conflict to other areas could not have been predicted. Moreover, the weapons, equipment and ammunition required by the Defence Forces are generally not available off the shelf and a lead time which can range from 4 to 18 months is required to produce and deliver them after conclusion of a contract.”

been at the forefront of an intense agitation against Fernandes on the issue, both inside and outside Parliament, during the NDA tenure.

Story continues below this ad

Today’s affidavit was a virtual U-turn from the earlier one and relied heavily on the CAG report which, it said, had “concluded that the excuse of Kargil was cited to push through procurements that would otherwise have been scrutinised more closely.”

The Government, so far, had scrutinised five transactions—hand-held thermal imagers, terminally guided munitions (Krasnapol), ammunition for T-72 tanks, ammunition and aluminium caskets—‘‘to fix responsibility…on the basis of the findings of the CAG’’, the additional affidavit said.

The other purchases that the CBI would be asked to look into include: illuminating ammunition for 155 mm guns (Rs 52.47 crore), special ammunition for 40 mm L-70 gun (Rs 166.44 crore), automatic grenade launchers (Rs 52.13 crores), spares for 155 mm guns (Rs. 97.65 crore), special clothing and mountaineering equipment (Rs 95.15 crore) and 155 mm red phosphorus ammunition (Rs 55.1 crore).

While the first two deals, which also figure in the Tehelka tapes, have been referred to the CBI for further probe, the rest are also being transferred to the agency, it said.

Story continues below this ad

The affidavit submitted that the Government was also exploring whether the facts reveal a prima-facie case of commission of criminal offences under law given that CAG had pegged the financial loss at over Rs 2000 crores, “in addition to the fact that the equipments did not materialise at the time of its need.”

Incidentally, the Government had stated in the earlier affidavit that the modified norms had not violated any financial rules of the government.

The April 5 affidavit had also explained the delay in the supply of arms thus: “At the time of making projections, the duration of operations, the nature and levels of conflict and the possibility of spread of the conflict to other areas could not have been predicted. Moreover, the weapons, equipment and ammunition required by the Defence Forces are generally not available off the shelf and a lead time which can range from 4 to 18 months is required to produce and deliver them after conclusion of a contract.”

Ananthakrishnan G. is a Senior Assistant Editor with The Indian Express. He has been in the field for over 23 years, kicking off his journalism career as a freelancer in the late nineties with bylines in The Hindu. A graduate in law, he practised in the District judiciary in Kerala for about two years before switching to journalism. His first permanent assignment was with The Press Trust of India in Delhi where he was assigned to cover the lower courts and various commissions of inquiry. He reported from the Delhi High Court and the Supreme Court of India during his first stint with The Indian Express in 2005-2006. Currently, in his second stint with The Indian Express, he reports from the Supreme Court and writes on topics related to law and the administration of justice. Legal reporting is his forte though he has extensive experience in political and community reporting too, having spent a decade as Kerala state correspondent, The Times of India and The Telegraph. He is a stickler for facts and has several impactful stories to his credit. ... Read More

Latest Comment
Post Comment
Read Comments
Advertisement
Advertisement
Advertisement
Advertisement