Stay updated with the latest - Click here to follow us on Instagram
The Yamuna Bank to Noida Sector-32 Metro corridor,which is scheduled to open for the public by the end of this month,is most likely to miss the deadline as Delhi Metro continues to face a shortage of trains. It also has the additional task of checking the piers on this completely elevated stretch. Two cantilever piers on this section were found to have cracks towards the end of last month on which corrective action is being taken.
The much-awaited Noida corridor will be the first Metro Rail project connecting the NCR but the DMRC is yet to get a final nod from the Urban Development Ministry to start operations in the NCR. Earlier this year,however,a bill to amend the Delhi Metro Railway (Operation and Maintenance) Act 2002,and the Metro Railway (Construction of Works) Act 1978 was passed by the Lok Sabha to expedite the Metro rail project in the NCR.
Metro officials maintained that the nod from the Urban Development Ministry does not look like much of a hurdle. The shortage of trains and the pending structural checks of the piers are the bigger roadblocks. An expert agency,Shirish Patel and Associates is looking into the cracks on the two piers on this line and corrective action is being taken.
DMRC doesnt want to take any chances now and hence the structural checks of the piers which were detected with cracks on this line are being put to critical tests and corrective action is being taken on them, said a DMRC official.
Though the official deadline for this project is October,the line was earlier scheduled for an early commissioning in June. But this was delayed due to a shortage of trains and the rescheduled internal deadline was set for August end. However,sources in the DMRC said that the line will require a minimum of seven to eight trains to begin with but the new trains that have arrived are all of a different make and the commissioning of these trains is thereby taking more time. While trial runs of these trains have begun,seven trains might not be ready for commissioning by end of this month.
Trial runs on a part of this stretch from Yamuna Bank to New Ashok Nagar were started on July 25. This completely elevated corridor,a 13.1 km stretch,with 10 stations will be an extension of the existing Blue Line (Line III – Dwarka Sector 9 to Yamuna Bank). Once operational,this will be the longest line of Delhi Metro and directly connect Dwarka Sector 9 to Noida City Centre in Sector 32.
Yamuna Bank to Noida Sec-32
Length of the line: 13.1 km
Total number of stations:
10out of which 4 fall in Delhi and 6 in Noida
Interim stations on the section: Akshardham,Mayur Vihar Phase I and Mayur Vihar Extension
Status update of the line
* Work on the section is almost complete and the viaduct and civil structure of stations is ready while the tracks and OHE have been completely laid till the Delhi border
* The Over Head Electric line has been energised till Noida Sector-15 and the finishing work inside the stations is in progress
Stay updated with the latest - Click here to follow us on Instagram