Stay updated with the latest - Click here to follow us on Instagram
By beating their earlier target of January 15, the Central Railway (CR) is likely to complete the construction of the 43-m bridge in Bhor Ghat in the next one week, work on which had caused many train services between Mumbai and Pune to be short-terminated.
These services are soon likely to run smoothly, with nearly 90 per cent construction completed, including the crucial girder launch.
The railways is now working on track construction and other overhead electrical fittings.
Services between Mumbai and Pune were disrupted after heavy rain in October damaged the approach to the bridge between Lonavala and Karjat.
A report by IIT Bombay had shown that the valley was adversely affected, following which the CR began reconstruction of the bridge. The 43-m bridge, a crucial connector of two tunnels, was broken into two small spans of 17 m and 25 m each.
A senior official from the CR said, “We brought a crane and assembled it on the site, using which we launched the two spans.”
The location of the work site also posed a massive challenge, as the concrete required for micro-piling to make a firm base could not be made at the site.
“We tied up with a company that supplied mixed concrete to prolong the settling time,” the official said.
Along with these measures, about 200 labourers were living at the site. The tracks will be commissioned with preliminary sanctions and will not require a clearance from the commissioner of railway safety, who has approved the basic design of the bridge. As the work is completed, inter-city train and shuttle services between Mumbai and Pune will be restored to normal, along with other long-distance trains, which are presently short terminated.
These services had to be halted as the up line (towards Mumbai) was shut, which reduced the capacity of the section that has three lines.
The work site, located over a 50 m deep valley about 147 km away from Mumbai, posed a challenge, as it has no road access. Shivaji Sutar, chief public relations officer of the CR, said, “We are hopeful to complete the work soon, following which the services will be restored. The work is on at a good pace.”
Stay updated with the latest - Click here to follow us on Instagram