Promised in 2015, pushed to 2026: Why Mumbai’s CSMT–Kurla 5th & 6th Line Project remains stalled and why it matters

Work of Phase 1 from Kurla to Parel in Mumbai is underway but beset by delays, mainly due to land acquisition problems; while the second phase, covering the Parel–CSMT stretch, remains only on paper.

Mumbai Local TrainPhase 1 of the CSMT-Kurla 5th & 6th rail line project covers the 10.1-kilometre segment from Kurla to Parel.

The long-delayed construction of two rail lines between Chhatrapati Shivaji Maharaj Terminus (CSMT) and Kurla, sanctioned 17 years ago under the Mumbai Urban Transport Project (MUTP-II) to ease congestion on Mumbai’s busiest rail corridor, is still far from completion. Back in 2010, then Chief Minister Ashok Chavan had assured that the 5th and 6th Line project would be ready and operational by 2015. A decade past that deadline, the first phase remains incomplete, with the target now pushed to 2026, while the second phase between Parel and CSMT has barely progressed due to space constraints. Naresh S examines where the project stands today and why its completion is crucial for Mumbai’s future.

What is the CSMT-Kurla 5th & 6th Line project?

The CSMT-Kurla 5th and 6th Line project, part of MUTP-II, was sanctioned in 2008 to decongest Mumbai’s busiest rail corridor by separating suburban local trains from mail, express, and goods trains. The project was originally sanctioned at around ₹800 crore, but the outlay has since risen to ₹1,337 crore. The project is divided into two phases, Phase 1 covers the construction of two new dedicated tracks between Kurla and Parel, while Phase 2 will extend the corridors from Parel to Chhatrapati Shivaji Maharaj Terminus (CSMT) in South Mumbai.

Phase 1: Kurla to Parel

Phase 1 covers the 10.1-kilometre segment from Kurla to Parel. Work is underway but beset by significant delays, mainly due to land acquisition problems involving slum rehabilitation, government, and private parcels.

Story continues below this ad

The progress of civil works for Phase 1 stands at around 28 per cent as of September 2025, with the official deadline for completion currently fixed at December 2025. But chances of extending the deadline to late 2026 are likely.

“There might be a delay in meeting the deadline, because there are still some issues with the land acquisition between Kurla and Parel. That is the biggest issue for the project,” said a Central Railway Public Relations Officer (PRO). Rehabilitation of more than 200 affected families in Vidyavihar and Sion has not fully progressed. Out of 212 families identified, around 140 have been shifted so far, with the rest pending.

Phase 2: Parel to CSMT

The second phase, covering the Parel–CSMT stretch of roughly 7.4 kilometres, remains on paper, with no construction or concrete land acquisition work started. Problems here are magnified by the dense development and layered property titles in South Mumbai. While officials are exploring technical options, including elevated or underground alignments, land handover, relocation, and urban complexity have kept Phase 2 dormant. “What is pending is only land acquisition and finalising technical studies. The work will not be scrapped,” said a railway officer.

How will the 5th and 6th lines benefit Mumbai?

Once commissioned, the new tracks will be reserved solely for express, mail, and goods trains, giving these services dedicated paths and freeing up the 3rd and 4th lines exclusively for suburban locals. Central Railway handles around 1,800 suburban services daily, carrying close to 35 lakh passengers on the CSMT–Kurla–Kalyan corridor.

Story continues below this ad

“Once completed, the 5th and 6th lines will be exclusively allotted for express, mail, and goods trains. The 3rd and 4th lines will be completely dedicated to suburban trains. This will reduce possible delays for suburban, express, and mail trains. The matter of increasing the frequency of suburban trains can’t be confirmed now, but the punctuality of the trains will be assured,” said a railway officer. Railway authorities have pointed out that track alignments and signaling requirements are designed for long-distance train operations, not suburban frequencies.

Stay updated with the latest - Click here to follow us on Instagram

Latest Comment
Post Comment
Read Comments
Advertisement
Loading Taboola...
Advertisement