Stay updated with the latest - Click here to follow us on Instagram
Work on the 653-km stretch of East-West corridor project in Uttar Pradesh is nearing completion as as per the officials in National Highways Authority of India (NHAI),the corridor is going to be completed by June this year,as almost all the sections of the highway are complete expect the construction of two Railway Over Bridges (ROB) one near Barabanki-bypass and one in Unnao on Lucknow-Kanpur highway. Work on minor stretches on Ayodhya bypass,Gorakhpur bypass and Lucknow bypass are also to be completed shortly.
All these remaining works are in final stage and are going to be completed by June, said AC Srivastava,Regional Officer,NHAI,UP.
Almost 90 per cent work has been done. Work on Lucknow-Faizabad sections has been completed by 98 per cent, Srivastava added.
The parts that have been completed include Jhansi bypass,Bara to Orai,Kasi to Gorakhpur,Orai to Jhansi. Sources said that most of these stretches were completed last year and opened for traffic. The Lucknow-Ayodha part is also complete except the ROB near Safedabad crossing. NHAI officials said the construction of ROB is taking long because of high rail traffic on the route.
The East-West corridor was started in 1998 under the National Highways Development Programme (NHDP) to connect Silchar in Assam to Porbandar in Gujarat. The four-lane corridor passes through Gujarat,Rajasthan,Madhya Pradesh,UP,Bihar,West Bengal and Assam. The total length of the corridor is 3,300-km.
In UP,the corridor connects the districts includingJhansi-Orai-Kanpur-Lucknow-Barabanki-Faizabad and Gorakhpur. The major hurdle,NHAI officials said,in executing the project was at first the delay in land acquisition and later the conditions stipulated by the state government for providing land strip for afforestation before allowing cutting of trees.
All such issues have been sorted out and the project is going to be completed this year, said an official of NHAI.
The 22-km Lucknow-bypass,also called Amar Shaheed Path,is likely to be completed by March. The 14-km stretch of the highway is open for traffic from Kanpur Road to Sultanpur Road. A two-km stretch between Chinhat trisection to Husandiyan crossing is also operational. Officials said that work on the remaining six-km stretch is at the last stage except the ROB in Gomti Nagar that could be completed by March.
Stay updated with the latest - Click here to follow us on Instagram