Railways sanctions Rs 396 crore for doubling Ranaghat-Bangaon section in West Bengal

Ranaghat-Bangaon rail line doubling: According to the railways, the doubling of Ranaghat-Bangaon rail line will help in decongestion of the section keeping in view the present capacity utilisation of 114% of the section thereby mobilising both passenger & freight traffic.

The doubling of this section will also create avenues for additional freight traffic of 0.88 MTPAThe doubling of this section will also create avenues for additional freight traffic of 0.88 MTPA. (Image: Ministry of Railways)
Advertisement

Railway project in West Bengal: The Railway Board has sanctioned Rs 396.04 crore for the doubling of Ranaghat-Bangaon section in West Bengal. The move aims at speedy completion of the rail project and enabling quicker movement of freight as well as of local passengers between adjacent districts Nadia and North 24 Parganas.

Ranaghat-Bangaon rail section

The 32.93-km-long Ranaghat-Bangaon section is a part of Eastern Railway’s Sealdah division. Ranaghat Jn is a station situated on Sealdah – Krishnanagar – Lalgola Main Line section whereas Bangaon is a Junction station situated at Sealdah/Kolkata- Dum Dum Bangaon – Petrapole (near Bangladesh border) section.

Doubling of Ranaghat-Bangaon rail section

The doubling of Ranaghat-Bangaon section will also enable seamless movement of freight & passengers from remote areas of different stations in the section, such as: Cooper’s Halt, Naba Raynagar Halt, Gangnapur, Majhergram, Akaipur Halt, Gopalnagar and Satberia to other part of West Bengal as well as to the other states in the country.

AC local train on Ranaghat-Bangaon rail section

Recently, AC EMU local trains service has been introduced between Ranaghat & Sealdah via Bangaon ( through Ranaghat-Bangaon route).

Significance of Ranaghat-Bangaon rail line doubling

According to the railways, the doubling of Ranaghat-Bangaon rail line will help in decongestion of the section keeping in view the present capacity utilisation of 114% of the section thereby mobilising both passenger & freight traffic.

“Once doubling work is completed there will be no detention for crossing of trains like in single line section and speedy movement will be established between Ranaghat & Bangaon. The doubling of this section will also create avenues for additional freight traffic of 0.88 MTPA and services of additional 10 passenger train per day in each directions over this stretch of double line between Ranaghat & Bangaon resulting in additional earning of ₹8.66 crore,” it said in a statement.

From the homepage

Anish Mondal is a business journalist with over nine years of experience. He writes on diverse subjects such as Infrastructure, Railways, Roadways, Aviation, Politics, Market, Parliamentary affairs, Corporate earnings, General and International news etc. ... Read More

Stay updated with the latest - Click here to follow us on Instagram

Tags:
  • Indian Railways Indian Railways news Ministry of Railways West Bengal
Edition
Install the Express App for
a better experience
Featured
Trending Topics
News
Multimedia
Follow Us
Bihar electionsThe importance of Sir Creek: Why India & Pakistan have failed to solve border dispute
X