Journalism of Courage
Premium

Subansiri landslides: CEA sought safety audits; NHPC said not needed

Monday’s landslide, the NHPC said, did not impact any project components or structure and would not further delay in commissioning the two units by June 2023.

Subansiri landslides: CEA sought safety audits; NHPC said not neededThe Subansiri hydel power project site in 2019. (File Photo)
Advertisement
Listen to this article Your browser does not support the audio element.

In April 2022, the Central Electricity Authority (CEA) advised the NHPC’s 2000-MW Lower Subansiri hydroelectric project, near North Lakhimpur along the Assam-Arunachal Pradesh border, to engage a specialised agency to examine the strength of the project’s powerhouse retention wall, and also assess the impact of diversion tunnels on the site’s slope stability before the onset of monsoon.

Read | Landslide hits Subansiri dam project; ‘Nothing to panic’, assures NHPC

The studies were not carried out. At least four major landslides have occurred since – the latest last Monday when boulders came crashing down the river’s left bank from the slope above the diversion tunnels.

A spokesperson for the NHPC said, “Since the monsoon had already set in since the last week of March 2022, the vetting by a specialised agency regarding the adequacy of the strength of the coffer wall and the site’s slope stability was not possible in view of heavy discharge in the river.”

Pointing out that the temporary coffer wall has been dismantled since and three of the five diversion tunnels have already been plugged, the spokesperson said: “Several studies were undertaken earlier… internally as well as by outside agencies… As such, no more assessment of landslide hazards and their impact was needed. The stability of adjoining mountains is being monitored by the NHPC design team and necessary stabilisation measures have been carried out as and when required.”

As recently as in March 2019, an expert committee report, based on which the National Green Tribunal (NGT) allowed the project work to resume, claimed that “the area is free from any major active landslide problem and no significant slope instability condition exists in the immediate vicinity of the dam.”

In April 2022, referring to a recent collapse of the project’s guard wall, a field inspection report by the CEA warned that “significantly higher flow predicted during monsoons would result in higher pressure” and “advised… that the adequacy of powerhouse protection wall’s strength” be “vetted by a specialised agency before the coming monsoons.”

Pointing out that continuous water flow through river diversion tunnels (DTs), which are meant to be temporary structures, might have eroded its walls, the CEA report said: “A reassessment of the impact of river diversion through DTs for such a long period on the slope stability of surrounding mountains may be carried out by NHPC.”

Story continues below this ad

Since its inception, the Lower Subansiri project has suffered multiple landslides. After work resumed in 2019, amidst gnawing safety concerns, the deadline for commissioning two of the project’s eight 250-MW units has seen four extensions: from March 2021 to August 2022, then to March 2023, and again to June 2023.

Monday’s landslide, the NHPC said, did not impact any project components or structure and would not further delay in commissioning the two units by June 2023.

The timeline of damages at the project site reveals a worrying pattern:

* January 2005: Project work begins.

* August 2005: Landslide hits surge shaft. A CAG report said the NHPC “stated that the contractor did not attend to the recommendations of the geologist despite communication from time to time.”

Story continues below this ad

* January 2008: Slope failure at the powerhouse, to quote a CAG report, “attributable to non-implementation of support measures suggested… by Design Division, non-availability of data on rock movements due to lack of proper calibration of the installed instruments and non-installation of survey targets and slope movement monitoring instruments.”

* December 2011: Local resistance stops project work.

* 2013-2018: Due to recurring damages, NHPC made multiple changes in the project design, settling for a surface powerhouse rather than an underground one. The changes were formally approved in March 2018.

* December 2015: NGT stays the already stalled project work.

* June 2019: The project gets final environment clearance. Work resumes.

* May 2020: Landslides hit the dam’s right bank following prolonged rain.

* June 2020: Heavy flooding damaged the diversion tunnels and the coffer dyke.

* July 2020: The guard wall of the powerhouse collapsed.

Story continues below this ad

* August 2021: The guard wall collapsed again and flood waters overflowed the dam.

* April 2022: The guard wall collapsed yet again. The CEA sought independent safety audits before monsoon.

* June 2022: The roof of the head race tunnel came unstuck, killing one.

* September 2022: Torrential rain broke part of the dam tunnel. A crater-like sinkhole was created. Landslides damaged diversion tunnels. The guard wall gave away and floodwaters entered the powerhouse.

* October 2022: A major landslide hit the diversion tunnels.

* April 2023: Yet another landslide above the diversion tunnel.

Jay Mazoomdaar is an investigative reporter focused on offshore finance, equitable growth, natural resources management and biodiversity conservation. Over two decades, his work has been recognised by the International Press Institute, the Ramnath Goenka Foundation, the Commonwealth Press Union, the Prem Bhatia Memorial Trust, the Asian College of Journalism etc. Mazoomdaar’s major investigations include the extirpation of tigers in Sariska, global offshore probes such as Panama Papers, Robert Vadra’s land deals in Rajasthan, India’s dubious forest cover data, Vyapam deaths in Madhya Pradesh, mega projects flouting clearance conditions, Nitin Gadkari’s link to e-rickshaws, India shifting stand on ivory ban to fly in African cheetahs, the loss of indigenous cow breeds, the hydel rush in Arunachal Pradesh, land mafias inside Corbett, the JDY financial inclusion scheme, an iron ore heist in Odisha, highways expansion through the Kanha-Pench landscape etc. ... Read More

Stay updated with the latest - Click here to follow us on Instagram

Tags:
  • NHPC
Edition
Install the Express App for
a better experience
Featured
Trending Topics
News
Multimedia
Follow Us
Muttaqi in IndiaWhy New Delhi is increasing engagement with Afghanistan's Taliban
X