Journalism of Courage
Premium

Some Smart Cities Mission projects to miss June 30 deadline, states must take over, , panel told

In its report on the evaluation of the Smart Cities Mission presented in the Lok Sabha on Thursday, the committee said the ministry had informed it that 400 projects, out of the 7,970, worth Rs 22,814 crore would take beyond December 2024 to complete.

Smart Cities Mission, smart cities project, Manoj Joshi, Indian express news, current affairsThe committee recommended that the next phase of the mission be brought for Tier-2 cities in the radius of 50-100 km of capital cities and tourist hubs.
Advertisement

Some projects under the Smart Cities Mission would not be able to meet the June 30 deadline and the respective state governments would be responsible for completing them thereafter, Union Housing and Urban Affairs Secretary Manoj Joshi told the Parliamentary Standing Committee on Housing and Urban Affairs.

In its report on the evaluation of the Smart Cities Mission presented in the Lok Sabha on Thursday, the committee said the ministry had informed it that 400 projects, out of the 7,970, worth Rs 22,814 crore would take beyond December 2024 to complete. Last year, the Ministry had extended the mission’s deadline from June 2023 to June 2024.

“The ministry has stated before the committee that in case of non-completion of these projects within the extended time frame, the state governments concerned will have to complete the projects at their own cost. The committee is of the strong opinion that the ministry’s role should not be confined to transfer of their share regarding mission/scheme/project, but they have to remain watchful for the execution and successful completion of the projects,” the report said.

The committee, chaired by JDU MP Rajiv Ranjan Singh, was told by Housing and Urban Affairs Secretary Manoj Joshi that the ministry did not want to extend the mission further.

Among the reasons cited by the ministry for the delays were difficulties in resettlement of local population and legal issues such as land procurement. Frequent transfers of smart cities’ CEOs and delay in projects that require convergence with other government ministries or agencies were also flagged.

As on December 1, the ministry said that out of 7,970 projects worth Rs 1,70,400 crore in the 100 cities, 6,419 projects worth Rs 1,25,105 crore have been completed and 1,551 projects worth Rs 45,295 crore are underway. Among the cities lagging behind were North-Eastern, Himalayan cities and those in small Union Territories.

“Progress of work is from 80% to 100% in 57 cities amongst which Madurai is the only Smart City which has completed 100% of smart city projects by December 2024. However, progress of work is 50% or below 50% in 14 cities. Gangtok, Atal Nagar, Shillong, Silvassa, Itanagar, Puducherry, Saharanpur and Port Blair have completed only 16%, 23%, 24%, 28%, 31%, 32%, 35% and 39% of projects so far respectively,” it said.

Story continues below this ad

The committee recommended that the next phase of the mission be brought for Tier-2 cities in the radius of 50-100 km of capital cities and tourist hubs. The committee also recommended that the right to privacy be protected, given that the mission had led to installation of over 76,000 CCTV cameras, Integrated Command and Control Centres in all 100 cities, red-light violation detection and smart health systems.

Stay updated with the latest - Click here to follow us on Instagram

Tags:
  • Smart Cities Mission smart cities project
Edition
Install the Express App for
a better experience
Featured
Trending Topics
News
Multimedia
Follow Us
Express PremiumNow a security ‘threat’, Sonam Wangchuk was Govt’s expert for all seasons
X