Projects delayed, costs go up for Delhi Metro

“The reason for the delay has primarily been lack of permission from the Delhi government’s environment department; files related to around 9 such projects were pending with the department till as recently as December last year,” a source said.

According to sources, theprojects are part of the Janakpuri to RK Ashram, Aerocity to Tughlakabad and Maujpur to Majlis Park corridors. (Express File)
Listen to this article Your browser does not support the audio element.

The cost of construction of at least nine projects related to the Delhi Metro’s network has escalated by almost 15% due to alleged delays in environmental clearance, it is learnt.

Critical corridors that are part of Phase-IV of the Delhi Metro Rail Corporation (DMRC), government sources said quoting approximations gathered from the DMRC, were running behind schedule for periods between three months to almost three years, pushing the combined cost of their construction up to over Rs 12,048.50 crore from initial estimates of around Rs 10,479.66 crore.

The Delhi government did not offer a comment on the issue.

“The reason for the delay has primarily been lack of permission from the Delhi government’s environment department; files related to around 9 such projects were pending with the department till as recently as December last year,” a source said.

“These files were recalledby the Lieutenant Governor’s Secretariat beginning early December 2022 and all of them have been cleared over the last two months following the L-G’s intervention,” the source added.

According to sources, theprojects are part of the Janakpuri to RK Ashram, Aerocity to Tughlakabad and Maujpur to Majlis Park corridors; the combined cost overrun for all the projects is around Rs 1,600 crore.

Due to the delays, a senior official explained, fresh bids for construction had to be called as per the re-tendering of work on these corridors on more occasions than one.

Story continues below this ad

“If a project is not completed on time due to one reason or another, the work is, after a certain interval, put up for a tender bid again. During this period, the cost of everything from construction material and labour among other components usually increases,” the official stated.

“In the case of these projects, the projected cost initially was Rs 10,479.66 crore and is now estimated to be Rs 12,048.50 crore,” the official added.

The project with the lowest delay, of over three months, is the construction of an underground ramp at Krishna Park Extension over a stretch of 2.01 kilometres with an initial cost of an estimated Rs 489 crore. Following the delay, the hiked total cost of construction is now estimated to have gone up to over Rs 550 crore, the official said.

Similarly, the official said, construction of the line from Sangam Vihar to Saket, over a stretch of around 4.2 kilometres, has been delayed for the longest period, that is by over 30 months. Its initial cost was Rs 726.08 crore, which is now estimated to have gone up to Rs 1,100 crore.

Story continues below this ad

A line measuring over 12 km on the Maujpur to Majlis Park corridor, supposed to initially cost

Rs 10.80 crore for construction between Yamuna Vihar to Bhajanpura and Sonia Vihar to Khajuri Khas and Sonia Vihar to Yamuna Bridge, is now expected to cost around Rs 16.50 crore, the official added.

Jatin Anand is an Assistant Editor with the national political bureau of The Indian Express. Over the last 16 years, he has covered governance, politics, bureaucracy, crime, traffic, intelligence, the Election Commission of India and Urban Development among other beats. He is an English (Literature) graduate from Zakir Husain Delhi College, DU & specialised in Print at the Asian College of Journalism (ACJ), Chennai. He tweets @jatinpaul ... Read More

Stay updated with the latest - Click here to follow us on Instagram

Tags:
  • delhi metro
Edition
Install the Express App for
a better experience
Featured
Trending Topics
News
Multimedia
Follow Us
Express ExplainedHow will the US government shutdown impact immigrants and visa holders?
X