Why 20 units threatened to move out of an auto hub near Pune, put government on watch

Set up in 1995, with a workforce of 10 lakh plus, and revenues of over Rs 6 lakh crore annually, Chakan MIDC area is tired of fighting power, water, traffic, even waste, issues

Pune: The road leading to Chakan MIDC from Nanekarwadi; The state of the roads. (Express Photos by Manoj More/Enhanced using AI)The road leading to Chakan MIDC from Nanekarwadi; The state of the roads. (Express Photos by Manoj More/Enhanced using AI)

An August 31 deadline to fill potholes; a one-month deadline to clear roadside encroachments; a 10-month timeline to improve infrastructure and waste collection; 100 private security personnel to manage traffic; and long-term plans for a truck terminal, power sub-stations, and a well-equipped hospital.

The Maharashtra government is scrambling to put its vaunted “automobile hub”, the Chakan MIDC (Maharashtra Industrial Development Corporation) in Pune district, in shape after an ultimatum by 20 industrial units to relocate elsewhere over their long-pending demand for basic amenities and infrastructure, while alleging “continued neglect”’ by the powers-that-be.

The Chakan MIDC – part of the larger Pune-Chakan-Talegaon industrial belt – came up in 1995, with the government offering tax incentives and a 50% subsidy on investment to units who moved to the area.

While automobile giant Bajaj Auto was the first major industrial unit to come up in Chakan, followed by hundreds of ancillary units, at least 10-15 large companies have units here spread over a 4,000-hectare area now, including Bajaj Auto, Hyundai, Mercedez-Benz, Skoda, Mahindra and Volkswagen.

Over 10 lakh workers are employed in these units.

‘Does Chakan matter?’

This monsoon, visitors to Chakan were greeted by potholes and craters across both the key roads leading to the MIDC area, as well as the arterial stretches. Traffic jams extended to kilometres, while waste lay rotting on the sides of roads, along with heavy vehicles, with few dedicated parking spaces.

Residents such as Santosh Yelwande, of Kharabwadi in Chakan, and Rupesh Jadhav of Nanekarwadi, talk of the situation worsening every monsoon. “’A stretch that used to take us 20-25 minutes now takes two-three hours,” says Jadhav.

Pointing out the number of jobs provided by Chakan’s units and the revenue generated to the tune of “Rs 6 lakh crore annually”, Chakan Industrial Association president Shantanu Kulkarni says: “We contribute estimated Rs 1 lakh crore in GST per year, besides about Rs 13,000 crore in income tax annually. The SME turnover, from the share of total revenue, stands at Rs 2 lakh crore… Despite this, does Chakan matter or not? For years, it hasn’t seemed so.”

Story continues below this ad
Pune The state of garbage. (Express Photo by Manoj More/Enhanced using AI)

He talks of daily power cuts running “over four hours” hitting operating costs and delaying deliveries, and a mismatch in road planning. “An MIDC road that is 70 metres wide in some stretches connects to an approach road just 8 metres wide, making commuting nearly impossible for the area’s large workforce.”

Dhananjay Shedbale, the owner of Deeksha Export Pvt Ltd, which has been operating in Chakan for 19 years and was among the 20 units that threatened to move out, says: “We get water for just over one hour. Sometimes there is no supply, without any notice… Several companies depend on tankers and end up halting water-intensive production.”

MIDC Executive Engineer Prakash Bhadange denies any water shortage. “We supply 30 MLD (million litres daily) water to Chakan MIDC. And this is sufficient,” Bhadange insists.

On power cuts, Shedbale says: “Be it operation, maintenance or distribution, there is a problem on every front… The power system badly needs an upgrade.”

Story continues below this ad

Executive Engineer Sandhya Banmikar admits that the current installed capacity “falls short of expectations of industrialists”. “Two new substations and two additional transformers are planned to increase the capacity.”

The decision to warn the government that they may relocate was not taken lightly, Shedbale says. “For over 14 months, we have been approaching several authorities, from the Chief Minister to Pune’s Divisional Commissioner Office, with little response.”

‘Severe infrastructure gap’: CM

The ultimatum by the Chakan firms was cited by the Opposition as evidence of the Maharashtra government’s failures. NCP (SP) national president Sharad Pawar urged the state government to act immediately to “protect Maharashtra’s industrial strength”. “We have always been an industry-friendly state,” he said.

Shiv Sena (UBT) spokesperson Sanjay Raut accused the Fadnavis government of “failing” industrialists. “The Mahayuti government simply does not care for industries. It just wants to milk them,” he said.

Story continues below this ad

After Chief Minister Devendra Fadnavis admitted “a severe infrastructure gap”, Industries Minister Uday Samant visited the MIDC area on August 16. Soon after, the government announced a 14-member committee to tackle Chakan’s issues, headed by the Pune District Collector as chairman and the Pimpri-Chinchwad Police Commissioner as co-chairman.

On a visit to Pune, Fadnavis said that apart from fixing immediate problems, his government was working out a long-term plan to convert MIDC areas into full-fledged industrial townships.

Pune District Collector Jitendra Dudi said measures to improve facilities such as roads, waste collection, power and water were on their way. “Only 10 per cent of the Chakan MIDC area has streetlights. Besides, most roads have encroachments… Henceforth, things will be drastically improved.”

According to him, it was “poor coordination” between government agencies – from the MIDC, road and water authorities, to municipal and panchayat bodies – that had hit Chakan’s plans. “We take the blame upon ourselves. We did not ensure proper coordination,” Dudi said.

Story continues below this ad

In the works is a plant that would be able to process 100 tonnes of waste generated by Chakan industrial units, two municipal councils and 19 villages; a meeting the coming week to discuss the water issue; and plans to make the Pune-Nashik highway a green corridor.

It happened in Hinjewadi

Last year, waterlogging during monsoons had prompted IT units located in the tech hub of Hinjewadi near Pune to threaten to shift to Bengaluru. At the time, the then Deputy CM Ajit Pawar had stepped in to reassure the firms, specifically directing officials to work on widening roads.

PMRDA officials claim that, unlike last year, this year there were hardly any complaints of waterlogging in the Hinjewadi area. An official said: “We have a concrete plan concerning roads and vehicular traffic ready, which we will be rolling out in September.”

Pavanjit Mane, who heads the Forum for IT Employees in Hinjewadi, says the problem of waterlogging is down but hardly removed. “The government has failed to keep its word.”

Story continues below this ad

Another promise, of road widening, is at a halt, says Mane. “’The space for widening was acquired by the government but people are protesting complaining inadequate compensation. In effect, even after the threat by IT firms to shift out of Hinjewadi, not much has happened in the past year.”

The Hinjewadi example is very much before the Chakan Industrial Association. “For now, the 20 industries have decided not to relocate from Chakan. They will wait till the 10-month deadline given by the government. In case things do not improve, the industries will take a call. More units will then follow suit,” says president Shantanu Kulkarni.

Manoj Dattatrye More is a Senior Editor at The Indian Express, having been with the publication since 1992. Based in Pune, he is a veteran journalist with a 33-year career that spans editorial desk work, investigative reporting, and political analysis. Professional Legacy Experience: He spent his first 16 years on the editorial desk before moving into active field reporting. He has written over 20,000 stories, including more than 10,000 bylined articles. Impact Journalism: He is widely respected for "campaign-style" reporting that leads to tangible social change. Road Safety: His decade-long campaign regarding the dangerous state of the Pune-Mumbai highway in Khadki resulted in a ₹23 crore reconstruction project in 2006, which dramatically reduced fatalities. Environmental Protection: His reports against tree cutting on the Pune-Mumbai and Pune-Nashik highways saved approximately 2,000 trees. Anti-Corruption: During the COVID-19 pandemic, he exposed a scam where doctors were being asked to pay bribes for government jobs, resulting in them being hired without payment. Recent Notable Articles (Late 2025) Manoj More's recent work focuses heavily on the shifting political landscape of Maharashtra and civic governance in the Pimpri-Chinchwad area: 1. Political Shifts & Alliances "Ajit Pawar's NCP continues domination in Pune, wins 10 of 17 local bodies" (Dec 21, 2025): A major report on the local self-government election results, detailing the NCP’s stronghold in Baramati, Indapur, and Lonavala. "BJP ropes in 13 ex-corporators, deals major blow to NCP" (Dec 20, 2025): Reporting on a significant political defection in Pimpri-Chinchwad as the BJP gears up for civic polls. "Congress opts for solo BMC run as alliance talks with Sena (UBT) collapse" (Dec 17, 2025): Covering the breakdown of Maha Vikas Aghadi (MVA) talks for the Mumbai civic elections. "NCP(SP)'s Rahul Kalate, Sena (UBT) leader Sanjog Waghere set to join BJP" (Dec 19, 2025): Detailing high-profile party-hopping ahead of the municipal elections. 2. Civic & Administrative Accountability "PCMC draws ire for issuing tenders worth Rs 250 crore just before poll code" (Dec 17, 2025): An investigative piece on the Pimpri-Chinchwad Municipal Corporation’s last-minute spending spree before election restrictions. "93 killed in 76 accidents in five years: Bypass service roads in Pune remain undeveloped for 18 yrs" (Nov 16, 2025): A critical look at the long-delayed infrastructure projects contributing to fatalities on Pune’s bypass roads. 3. Social & Labor Issues "As state says TCS has laid off 376 employees: FITE flags figures, say nearly 2,500 were forced to quit" (Dec 11, 2025): Investigating conflicting reports regarding IT sector layoffs in Maharashtra. "Maharashtra govt move to 'downgrade' Aadhaar cards" (Nov 30, 2025): Reporting on the state’s decision to require additional documents alongside Aadhaar to combat identity misuse. Signature Beat Manoj More is the definitive voice on Pimpri-Chinchwad, an industrial hub he has covered for three decades. His reporting is characterized by its aggressive stance against local "gondaism" (thuggery) and a relentless focus on civic infrastructure—choked drains, garbage management, and public transport. X (Twitter): @manojmore91982 ... Read More

Shubham Kurale is a journalist based in Pune and has studied journalism at the Ranade Institute. He primarily reports on transport and is interested in covering civic issues, sports, gig workers, environmental issues, and queer issues. X:@ShubhamKurale1 ... Read More


Click here to join Express Pune WhatsApp channel and get a curated list of our stories

Advertisement
Loading Recommendations...
Advertisement
Advertisement
Latest Comment
Post Comment
Read Comments