Ministries of coal,power up in arms over MoEF proposal

Forest clearance for projects z Oppose move to double deadline to 300 days,argue it will lead to further delay

Written by Anubhuti Vishnoi | New Delhi |
November 16, 2013 3:31:25 am

The proposal for a longer and arguably more “realistic” timeline for clearance to projects needing forest land has two key ministries up in arms. The Ministry of Power and Ministry of Coal are opposing the Ministry of Environment & Forests (MoEF) move to double the 150-day limit for processing forest clearance proposals to 300 days for projects involving diversion of over 100 hectare forest land.

The two ministries have repeatedly attributed delays in projects to cumbersome procedures in seeking green clearance. The Jayanthi Natarjan-led MoEF has decided to amend Forest Conservation Rules to usher in more ‘realistic’ limits that can be met,and which allow more time to both the State and the Centre to assess projects that need forest clearance.

The draft rules were circulated to all concerned ministries. The power and coal ministries argued that it will only delay clearances further and hold back projects.

The draft rules proposed 140 days for smaller projects needing up to 5 hectare land.

Best of Express Premium
UPSC Key-June 27, 2022: Know the relevance of ‘Deputy Speaker’ to ‘Nation...Premium
An IITian, a convict serving life, and a ‘whistleblower’ cop:...Premium
Road to 2024: As BJP fills gaps ahead of next LS polls, Droupadi Murmu is...Premium
MYn wants to be India’s next big ‘super-app’ with unique take on privacyPremium

The present blanket rule asks states to examine and recommend fresh forest clearance proposals within 90 days (3 months) of receipt of the proposal from the user agency and for the Centre to reject/approve it within 60 days,but the process is said to drag on,for even two years or more.

The proposed rules have timelines depending on land. Total time including the procedures at the State and Central levels,sets a 140-day limit for processing forest land diversion up to 5ha,and 300 days for projects involving diversion of over 100 hectare of forest land.

A project involving diversion of 5ha,will thus be processed faster than one involving over 100ha. The proposed rules suggest detailed and tiered (for diversion of 5ha,5ha-40ha,40ha-100ha and over 100ha) timeline at each level from the state to the Centre including transit period,so the time frame is ‘realistic’ and ‘workable’.

The proposed rules say that in case a state government exceeds the stipulated timeline,it will have to explain the delay,and details of action taken against the individual responsible and only then will the Centre consider the proposal.

Express Subscription Do not hit the wall, subscribe for the best coverage out of India starting at just $5 per month

📣 Join our Telegram channel (The Indian Express) for the latest news and updates

For all the latest News Archive News, download Indian Express App.

  • Newsguard
  • The Indian Express website has been rated GREEN for its credibility and trustworthiness by Newsguard, a global service that rates news sources for their journalistic standards.
  • Newsguard
Advertisement
Advertisement
Advertisement
Advertisement