Hit by fuel shortage,power projects running at partial capacity only

The continuing shortage of fuel is clearly the biggest impediment

Written by: Anil Sasi
4 min readNew DelhiMar 11, 2013 01:29 AM IST First published on: Mar 11, 2013 at 01:29 AM IST

On paper,a cumulative thermal power generation capacity of 30,419 mega watts is reported to have been added during the last two years,an impressive increase of 27 per cent. But when it comes to actual electricity generation on the ground,the corresponding rise is just 15 per cent. The reason: most of the power generation projects commissioned since March 2009 are either idling or forced to operate at partial load.

The continuing shortage of fuel is clearly the biggest impediment,with domestic coal stocks alarmingly low and gas production having hit rock bottom. Added to this are some structural issues,including the fact that Coal India Ltd CIL has stopped signing fresh fuel supply agreements FSAs with power generation projects. Even in cases where FSAs have been signed,CIL is not willing to release coal to projects that do not have firm power purchase agreements or PPAs with distribution utilities in the states.

Latest Comment
Post Comment
Read Comments