Rajasthan’s power crisis may be far from over but the state has decided to disconnect from the Ravatbhatta atomic power plant, forcing the plant to cut production to 70 per cent and rethink setting up new units in the region.
Even as Rajasthan gets ready to switch on a 220 MW power plant in Kota this month, 50-odd km away, the Ravatbhatta atomic plant has reduced production, dug up unpaid bills and set the stage for a stand-off with Gehlot government. ‘‘They don’t want the power and since last week we have reduced production to 70 per cent,’’ says Subhash Mittal, plant director. ‘‘It is unfortunate as two units mainly catered to Rajasthan and we gave them preference. Now they don’t want it.’’
The government argues that buying power from Ravatbhatta is no longer economical and they don’t need all the electricity the plant generates since demand has dipped after the monsoons swept through the state. Energy Department data says the demand for power in the state has dipped by 500 MW due to monsoons. Further, the state has augmented its production by 520 MW, resulting in a net difference of 1020 MW. ‘‘They are too expensive,’’ says an official from Power and Energy Department. ‘‘And it’s not just us who are saying this. Other states buying power from Nuclear Power Corporation Limited NPCL agree with us. There has to be some rationale behind the pricing.’’
Mittal doesn’t buy the argument. ‘‘They can’t suddenly say we are expensive. Anyway look at their dues. Since March this year, the state has run up a bill of Rs 100 crore and they also have outstanding dues.’’ NPCL officials say that units three and four were inaugurated in 2000, based on the Rajasthan’s requirements.
But in the last four years, Rajasthan has increased production tremendously. ‘‘In fact, we are self-sufficient in our off-season or off-peak time demands,’’ says Energy Secretary C.S. Rajan, the man credited with power reforms in the state. ‘‘During peak hours, we have a deficit of about six to seven per cent only.’’
Energy Department officials say Rajasthan agreed to buy power from NPCL at a negotiated cost of Rs 2.78 per unit after seven of the eight states in the Northern Grid had said no. But now, the state feels the costs are too high. Moreover, the cheaper option of buying power from unit 1 no longer exists since it closed over a year ago. With all the escalation, the Rajasthan government is paying about Rs 3.14 per unit right now. Further, Energy Department officials add that to be able to absorb the power generated at Ravatbhatta, the state had to reduce its own production.
‘‘Again we are not the only ones unhappy with the situation,’’ an official says. ‘‘In fact, AP is not able to optimally use its hydel power because it has to buy power from NPCL and therefore reduce its production.’’ Officials add they will buy from NPCL but it should make their prices a little more competitive.