VADODARA, July 7: Nearly a month after its property and equipment were badly damaged due to cyclone, power supply remains to be restored in only 328 of the more than 18,000 villages by the Gujarat Electricity Board GEB.
According to an official spokesman, till Tuesday 11,603 km of high tension lines and 8,983 km of low tension lines and 4,611 transformer centres have been restored.
The spokesman said it was not possible to restore power supply in terminals of the Indian Oil Corporation IOC in Kandla as the area was still water-logged. He further said it was also not possible to supply power to the Kandla-Bhantida pipeline.
He said to expedite the work, the GEB had decided to lay an overhead line. The restoration was monitored on a round-the-clock basis by Board member Technical K K Vaghela.
According to official sources in the Gujarat Electricity Borard , the Board has procured 19,388 electricity poles from pole factories of Gujarat and 2,880 poles were received from the Maharashtra State Electricity Board. The spokesman further said Maharashtra was yet to send 1,800 poles as per allotment.
The spokesman said the quantity of poles available at present would be enough to meet requirements of various electricity circles. He further stated that as nearly a lakh poles were expected to be produced in 3 to 4 months, there will be no need to purchase more poles from other parts of the country.