8226; The Taj Expressway Project, being a landmark even of the industrial development of the state of Uttar Pradesh, is of immense public utility and also in the national interest.
8226; The contract as per the Concession Agreement dated February 7, 2003 is a lawful, valid and still subsisting contract, enforceable in law.
8226; The costs and obligations, agreed in the contract, were based on policy decisions of the state government, after due deliberations while preparing the bid documents and those would be deemed to be adequate on the facts and in the circumstances of the case.
8226; M/s Jaiprakash Associates Limited is required to form/float a special purpose vehicle for the contract as coveted in the Concession Agreement. The state government would be better advised to do the needful for settlement of the terms of the relevant deed without disturbing the basic tenet of the Concession Agreement in due course of time.
8226; M/s Jaiprakash Associates Ltd is also under contractual obligation to submit TEFR without any further delay.
8226; The state government of Uttar Pradesh as also the parties to the contract, that is, the Taj Expressway Industrial Development Authority and M/s Jaiprakash Associates Limited and any person/organisation deriving right, title and interest through them, would be lawfully bound by the terms and conditions of the contract under the Concession Agreement as construed in the right perspective, in respect of their respective rights and obligations.
8226; The terms and conditions of the contract as stipulated in the Concession Agreement and any deed or document executed thereunder have to be construed in totality and not in isolation with the ultimate aims and object of the government policy as reflected in the Uttar Pradesh Industrial Area Development Act 1976 Act No. 6 of 1976 and other allied statutes, bye-laws, master plan and building regulations, directions as framed thereunder and the policy of the state government UP.
8226; The prosecution of the project work is emergent and should proceed ahead with immediate effect while removing the deadlock at any level.
8226; The parties to the contract are at liberty to pursue and enforce the accomplishment of reciprocal promises and obligations under the contract without any further loss of time.
8226; The lease of about 250 hectares of land for development in Stage-1 in favour of M/s JAL was consistent with the terms and conditions in the bid documents and also the Concession Agreement dated 07.02.2003, determined as a result of due deliberations at various stages.
8226; The State Pollution Control Board may now be better advised to expedite its process as to grant of Environmental Clearance Certificate without any further delay.
8226; In the face of obligations undertaken by M/s JAL, there was no necessity of performance guarantee/security.
8226; The Taj Expressway Authority must now make regulations with the previous approval of the state government for administration of the affairs of the Authority including extent of delegation of powers to its Chief Executive Officer and, in particular, regarding conduct of business at the board’s meeting as provided under Section 19 of the UP Industrial Area Development Act 1976. The state government also may, by notification, make rules in exercise of powers under Section 18 of the said Act.
This report is being submitted three weeks ahead of the extended period of this inquiry for reasons of expediency and also time being the essence of the contract. It shall, however, be open for the state government to seek any needed clarifications and/or further suggestions in the matter of this report.