While travellers dream of zipping from one corner of the country to another on the Golden Quadrilateral, Anwar Singh knows better.
For the time being, at least, the remains of that ambitious dream lie buried in his field.
Officially, this is Phase 1B, the Shikohabad-Etawah stretch of the Golden Quadrilateral. It is supposed to link Delhi and Kolkata. Instead, it is sending mud and slush on to Anwar Singh’s fields, as work has come to a complete halt.
Meanwhile, officials are counting the cost of awarding projects to the lowest bidders who then find themselves unable to deliver.
The Chinese firm that was supposed to construct this 59.02 km stretch has had its contract terminated for non-performance. It was supposed to have completed nearly 67 per cent of the project by June. Instead, it has barely completed 8.88 per cent. This could delay the stretch by a year.
Travellers, hoping for a uniformly smooth ride, will pay the price later. Anwar Singh is doing so now.
From the leaking bypass that runs through his fields, he has had to ‘‘physically pour out buckets of slush on both sides of his field’’. Meanwhile, his brother Lekham has lost his cauliflower crop, thanks to the dust and mud that settles on leaves and flowers.
The China Coal Construction Group Corporation CCCGC had bid just Rs 157 crore for this stretch. ‘‘That is practically 60 per cent of what it should have been,’’ says Ashwani Kumar, project director, National Highways Authority of India.
When costs on the ground rose, the Chinese could not sustain their work. NHAI has scrapped their contract, along with that of the Indo-Malaysian joint venture on the Ganjam-Icchapuram stretch. For many involved with the project, it was a disaster waiting to happen. Engineers who worked with them say the Chinese could hardly converse in English, knew nothing about working in India and used to enforce irregular working hours—7 a.m. to 11 a.m. and again after 6 p.m.
Now their equipment worth over Rs 20 crore lies rusting on the road. The matter has gone to court as the CCCGC cites ‘‘innumerable encroachments’’ as one of the reasons for delay. It also blames equipment theft and floods.
Ironically, the World Bank, which is funding the project, had touted Phase 1B as one of the best segments on the GQ as it was relatively free of encroachments.
Now the finger-pointing has begun, even as NHAI prepares to float another tender in three months.
The excuses will not matter to the commuters, who will have to encounter this nasty bottleneck in the middle of nowhere when the Delhi-Kolkata route is unveiled by December 2005.
They are of no consolation to those who run the filling station at Makkhanpur, right where Phase 1B starts. ‘‘The Chinese contractors dug up the space in front of our petrol station and left it like that. Now, most trucks have stopped coming,’’ says Ramji Lal, who works there. Daily sales have dropped from 10,000 litres to 2,000 litres, he says.
Now, even the earth work does by the Chinese contractor is being eroded. The earth level has already fallen by several centimetres, say NHAI officials.
Apart from rising costs, this could mean at least a year’s delay and the stretch may only be completed by December 2006, says Kumar.
And till that happens, there are no answers for people like Ganga Devi and her 84-year-old husband Raghuvir, who wait for their one-storeyed house to be pulled down. Like many in Katphodi village nearby, they were asked to move out to get the Shikohabad-Etawah stretch going. Says Ganga Devi: ‘‘Koi to bataye kab ghar giraye jayenge.’’Will someone tell us when our houses will be demolished.