Meanwhile, stretch he was working on remains grounded

A full year after Satyendra Dubey8217;s murder, the GQ stretch, where he worked, continues to languish. And the delays are both because of ...

.
Written by: Amitav Ranjan
2 min readNew DelhiNov 27, 2004 12:00 AM IST First published on: Nov 27, 2004 at 02:17 AM IST

A full year after Satyendra Dubey’s murder, the GQ stretch, where he worked, continues to languish. And the delays are both because of lawlessness and the presence of the law.

A 60-km stretch between Aurangabad and Barachatti has achieved 27 percent progress against the targeted 80 percent. It’s no better on the 78.75-km section, connecting Gorhar and Barwa Adda, where 32 percent of the job has been completed against the targeted 80 percent.

Advertisement

Just before Dubey’s murder, exactly a year ago, the progress in both sections was one-fourth the target.

Both projects are scheduled for completion by March 2005 but sources said they may take three more years because of CBI and CVC enquiries, and bad law and order situation.