Premium

Pay Rs 43 lakh with 18% interest for possession delay, SC tells builder

The apex court’s move was an outcome of a question raised by Sharma to a bench of Justice Dipankar Datta and AG Masih.

Pay `43 lakh with 18% interest for possession delay, SC tells builderThe apex court’s move was an outcome of a question raised by Sharma to a bench of Justice Dipankar Datta and AG Masih.
Written by: Ananthakrishnan G
2 min readNew DelhiSep 26, 2025 03:14 AM IST First published on: Sep 26, 2025 at 03:14 AM IST

The Supreme Court asked real estate developer — M/S Business Park Town Planners Ltd — to repay the amount invested by plot buyer Rajnesh Sharma (Rs 43.13 lakh) with 18% interest, 9% more than what was allowed by the National Consumer Disputes Redressal Commission (NCDRC).

The apex court’s move was an outcome of a question raised by Sharma to a bench of Justice Dipankar Datta and AG Masih. He asked: If a real estate company can charge 18% interest from plot buyers for defaulting payments, why should the former not be asked to pay similar interest to the latter for delaying plot handover?

Advertisement

Partly allowing Sharma’s appeal against the NCDRC order, the bench said, “We find that in all such cases this court did not give elaborate reasons for rejecting the claim for parity but reduced/increased the rate of interest based on factors peculiar to the facts and circumstances of each case, such as the market conditions, lockdown due to Covid, etc.”