Paid Rs 19 lakh but ‘no flat’ 8 years on, senior citizen wins possession, Rs 2 lakh relief

The consumer commission rejected the builder’s argument that the delay was due to COVID-19, pointing out that the handover was already delayed before the pandemic's outbreak.

haryana flat consumer court possessionThe possession of the flat was expected by March 2019, the commission noted, and rejected the builder’s claim that the Covid-19 pandemic and lockdown affected construction work. (AI-generated image)

A Haryana consumer body has found a builder deficient in service and indulging in unfair trade practices after it allegedly failed to deliver possession of a flat to a 73-year-old homebuyer despite receiving the entire basic sale consideration of Rs 19.62 lakh by November 2018.

The Rohtak Consumer Disputes Redressal Commission directed the builder to hand over peaceful possession of the flat within 30 days and to pay 9 per cent annual interest on the Rs 19.62 lakh from November 24, 2018, until actual possession, besides Rs 2.10 lakh towards compensation and litigation expenses.

President Nagender Singh Kadian, along with members Dr Tripti Pannu and Dr Vijender Singh, was hearing the complaint filed by a Haryana man who was allotted a flat in 2015 and was expecting possession by 2019 but allegedly never received it.

“The complainant, who is a senior citizen, has been deprived of the use and enjoyment of the flat despite making the substantial payment and arranging housing finance for the same. We are, therefore, of the considered view that there is clear deficiency in service on the part of the opposite parties,” the August 17 order read.

‘No possession’

The complainant claimed that he was allotted a flat in Panchkula by an allotment letter dated August 26, 2015. Thereafter, a flat buyer’s agreement was executed between the complainant and the builder on March 21, 2016. As per the agreement, the basic sale price of the flat was Rs 19.62 lakh.

The man claimed he took a loan to pay the sale amount for the flat. He added that the builders were bound to give possession within four years, but despite making the required payments, he did not receive possession of the flat. Aggrieved, he moved the commission seeking compensation for the loss and inconvenience suffered by him.

Builder’s defence

One of the builders, through its advocate, argued that under the agreement, the date of delivery of possession was tentative and subject to the force majeure clause, which was in the knowledge of the complainant. A force majeure clause in a contract temporarily (sometimes permanently) excuses parties from legal obligations when extraordinary, unforeseeable events make it impossible to carry it out. It was added that due to the emergence of the Covid-19 pandemic, the real estate sector and construction projects were seriously hampered.

Story continues below this ad

The lawyer submitted that the agreement contained a payment plan under which the complainant was to make the due instalments, but he stopped making further payments despite several demand letters, call notices and reminders.

It was argued that the complainant himself breached his obligation to make the entire and timely payment of the instalments and caused losses to the builders, as they had kept one of the apartments reserved for the complainant for a considerable period of time without payment of the agreed instalments. Advocates Ashuthosh Kumar Shrivastav and Rajesh Sharma represented the builder.

‘Can’t take shelter of pandemic’

The commission noted that the possession of the flat was expected by March 2019 and rejected the builder’s claim that the Covid-19 pandemic and nationwide lockdown affected construction activity. “The agreed period for delivery of possession had already expired before the commencement of the nationwide lockdown on March 25, 2020. Therefore, the opposite parties cannot take shelter under the Covid-19 pandemic for a delay which had already occurred before the pandemic began,” it added.

Holding that a consumer who has invested his hard-earned money in a residential project cannot be made to wait indefinitely for possession, the commission held that a builder is under an obligation to complete the project and hand over possession within the agreed period, failing which the consumer is entitled to appropriate compensation for the delay.

Story continues below this ad

Noting that the builders retained and utilised the amount of Rs 19.62 lakh paid by the complainant while failing to deliver possession within the given period, the commission directed them to pay interest at the rate of 9 per cent per annum on the said amount from November 24, 2018, when the entire basic sale consideration stood paid, till the date of actual delivery of possession to the complainant.

The commission directed the builders to complete any remaining construction and development work and hand over actual, physical and peaceful possession of the said flat to the complainant within 30 days.

The commission also directed the builder to pay an amount of Rs 2 lakh to the complainant as compensation for mental agony, harassment, financial inconvenience, and deficiency in service caused due to the inordinate delay in handing over possession of the flat, along with Rs 10,000 towards litigation expenses, within 30 days.

Takeaway

This ruling highlights that a builder cannot indefinitely delay possession after receiving the buyer’s money or seek shelter under reasons such as the Covid-19 pandemic when the agreed possession period had already expired.

Story continues below this ad

For consumer-related grievances, individuals may contact the consumer helpline in their respective states and Union territories (Kerala: 1800-180-2087) or call the National Consumer Helpline at 1915 for assistance.

Don’t miss out on these stories:

Stranded with aged parents after hotel ‘refuses’ dog, family wins Rs 1 lakh payout

Publisher took Rs 8,000 but ‘never published’ book, Punjab advocate wins Rs 23,000

Israel conflict cited for job delay, Kerala man given ‘fake flight booking’ wins Rs 5.8 lakh

Richa Sahay is a Legal Correspondent for The Indian Express (Digital), where she focuses on simplifying the complexities of the Indian judicial system. A law postgraduate, she leverages her advanced legal education to bridge the gap between technical court rulings and public understanding, ensuring that readers stay informed about the rapidly evolving legal landscape. Expertise Advanced Legal Education: As a law postgraduate, Richa possesses the academic depth required to interpret intricate statutes and constitutional nuances. Her background allows her to provide more than just summaries; she offers context-driven analysis of how legal changes impact the average citizen. Specialized Beat: She operates at the intersection of law and public policy, focusing on: Judicial Updates: Providing timely reports on orders from the Supreme Court of India and various High Courts. Legal Simplification: Translating dense "legalese" into accessible, engaging narratives without sacrificing factual accuracy. Legislative Changes: Monitoring new bills, amendments, and regulatory shifts that shape Indian society. ... Read More

 

Advertisement
Loading Recommendations...
Advertisement
Advertisement
Latest Comment
Post Comment
Read Comments