Railways targets to complete these 8 Mumbai-Ahmedabad bullet train stations by 2027

Bullet Train Project in India: The Ministry of Railways is working in full swing for the completion of India's first bullet train project. The 508-km-long bullet train project stretches from Mumbai to Ahmedabad.

The Mumbai-Ahmedabad bullet train corridor will have 12 stations.The Mumbai-Ahmedabad bullet train corridor will have 12 stations. (Image: Ashwini Vaishnaw/X)
Written by: Anish Mondal
3 min readJul 29, 2025 09:09 AM IST First published on: Jul 28, 2025 at 06:40 PM IST

Mumbai-Ahmedabad Bullet Train Project: The Ministry of Railways is working in full swing for the completion of India’s first bullet train project. The 508-km-long bullet train project stretches from Mumbai to Ahmedabad. The Mumbai Ahmedabad High Speed Rail (MAHSR) corridor is being implemented by the National High Speed Rail Corporation Limited (NHSRCL).

Mumbai-Ahmedabad Bullet Train Project Cost

The Mumbai-Ahmedabad bullet train project is being developed at a total estimated cost of Rs 1,08,000 crore. Out of these, Cumulative Financial expenditure of Rs 78,839 crore has been incurred on the project till June 30, 2025.

Advertisement

Mumbai-Ahmedabad Bullet Train Latest News

The Ministry of Railways is targeting to complete Gujarat portion of the Mumbai-Ahmedabad bullet train by 2027. In a written reply in Lok Sabha on July 23, Railway Minister Ashwini Vaishnaw said, “The Gujarat portion of the corridor between Vapi and Sabarmati is planned to be completed by Dec, 2027.”

Anish Mondal is a journalist with over nine years of experience covering the railways and roadways. ... Read More