Passenger trains to run at speed of up to 100 kmph on Mizoram’s Bairabi–Sairang railway line

Bairabi to Sairang Railway Line: Built at a cost of about Rs 8,000 crore, the 51.38-km-long Bairabi-Sairang railway line is an engineering marvel. The railway line project has set direct rail connectivity to the state capital, Aizawl, for the first time.

Earlier this year, the Commissioner of Railway Safety (CRS) authorised the commissioning of the newly constructed Broad Gauge (BG) line from Hortoki to Sairang, the final leg of the Bairabi–Sairang rail line project.Earlier this year, the Commissioner of Railway Safety (CRS) authorised the commissioning of the newly constructed Broad Gauge (BG) line from Hortoki to Sairang, the final leg of the Bairabi–Sairang rail line project. (Express Photo)
Written by: Anish Mondal
3 min readSep 13, 2025 12:46 AM IST First published on: Sep 8, 2025 at 02:57 PM IST

Railway project in Mizoram, Bairabi-Sairang railway line: The long-anticipated dream of rail connectivity to Aizawl is set to become a reality today. The Bairabi–Sairang railway line, a prestigious infrastructure project in Mizoram, will be inaugurated by Prime Minister Narendra Modi. Once operational, the new line will cut travel time between Aizawl and Silchar from nearly seven hours by road to just three hours by train. The passenger trains can run at speeds of up to 100 kmph on the newly built rail line.

Bairabi-Sairang railway project

Built at a cost of about Rs 8,000 crore, the 51.38-km-long Bairabi-Sairang railway line is an engineering marvel. It consists of 48 tunnels, 55 major bridges and 87 minor bridges. The total length of tunnels in this project is 12,853 meters. The height of bridge no. 196 is 104 meter which is 42 meter taller than the Qutub Minar.