Ahead of anniversary, PM’s J&K package audit: 50% funds used, third of projects done

In the last about five years, only nine projects have been fully “completed”, and eight more “substantially completed” in J&K. The outlay for this set of 17 projects stood at Rs 10,465 crore, which is less than a fifth of the total package for the Union Territory.

Written by: Naveed Iqbal
5 min readSrinagarJul 27, 2020 08:47 AM IST First published on: Jul 21, 2020 at 04:10 AM IST
Ahead of anniversary, PM’s J&K package audit: 50% funds used, third of projects done Officials in the UT administration said in June 2018 (when President’s rule was imposed in the erstwhile state of J&K), the funds released under PMDP stood at 26 per cent.

Nearly five years since the announcement of the Prime Minister’s Development Package (PMDP) for Jammu and Kashmir, only 49 per cent of the funds allocated towards 54 projects (excluding Ladakh) has been utilised, according to a review undertaken by the administration in July.

The review splits the PMDP outlay for the Union Territories of Jammu and Kashmir, and Ladakh. Of the Rs 58,627 crore allocated for the Union Territory of J&K, only Rs 28,768 crore has been utilised. The package was announced by Prime Minister Narendra Modi at a rally in Srinagar on November 7, 2015. J&K was a state then, run by a BJP-PDP coalition, with Mufti Mohammad Sayeed as the Chief Minister.