Thane: Bullet train station redesigned to reduce impact on mangroves

Maharashtra Transport Minister Diwakar Raote had said on Monday in a reply to a question in the state Legislative Council that as many as 54,000 mangroves spread over 13.36 hectares will be affected because of the Mumbai-Ahmedabad High-Speed Rail Corridor.

Bullet Train, Bullet Train india, Bullet Train mumbai, Bullet Train thane, ahmedabad mumbai Bullet Train, NHSRCL, Bullet train station, Mangrove forests, Thane station NHRSCL has reworked the design to reduce the number of affected mangroves. (Express Archive)

NHSRCL, the implementing agency of the Railways’ bullet train project, said Saturday that they have reworked the design of the station in Thane, Maharashtra, to reduce the number of affected mangroves from the estimated 53,000 to 32,044.

National High-Speed Rail Corporation Limited (NHRSCL) MD Achal Khare said in a statement that all the required wildlife, forest and CRZ clearance has been taken. He said the forest clearance came with a few conditions. The Environment Ministry had put a condition that the Thane station design is reviewed so that the affected mangrove region can be reduced.

“That without changing the location of Thane station, in what all ways can we reduce the Mangrove region – this is what we discussed that design with Japanese engineers and modified it accordingly,” Khare said.

“Passenger areas like the parking area and passenger handling area have now been moved out of the mangrove region. The location of the station is the same but after redesigning it, earlier 12 hector mangrove region was getting affected in Thane, but now only three hectors will get affected. So this way, we have reduced around 21,000 mangroves and now only 32,044 mangroves will get affected by the entire project. Earlier there were around 53,000 mangroves getting affected,” he said.

Subscriber Only Stories
From The Explained editor: The ban on PFI, forests at night, and free gra...Premium
From the Opinion Editor: An election for the Congress partyPremium
From Nehru to JP, the political leaders mentored by GandhiPremium
Uttarakhand resort murder: Amid questions within, BJP may revamp Dhami go...Premium

Khare further said that the NHSRCL will get the mangroves affected by the bullet train project compensated at the rate of 1:5, by depositing money into mangroves cell, which will do the compensatory afforestation. “So the number of mangroves which are getting cut is 32,044. Then around 1,60,000 new mangroves will be planted and the entire financial expense will be borne by NHSRCL. New mangroves will be planted through mangrove cells,” he added.

Earlier, Maharashtra Transport Minister Diwakar Raote had said on Monday in a reply to a question in the state Legislative Council that as many as 54,000 mangroves spread over 13.36 hectares will be affected because of the Mumbai-Ahmedabad High-Speed Rail Corridor.

First published on: 29-06-2019 at 11:35:11 am
Next Story

G-20 summit: A breakfast invitation helps rebuild a Crown Prince’s standing

Latest Comment
Post Comment
Read Comments
Advertisement
Advertisement
Advertisement
Advertisement