The 42-km rail track from Fazilka-Abohar will begin operation on Monday when Union Minister of state for railways K H Muniyappa will formally give the green signal,fulfilling a long pending demand of the locals. The rail link will be a boon for the locals as road transport fair from Fazilka to Abohar is more than Rs 20 while a train ticked will cost Rs 6.
The foundation stone of the project was laid in February 2004 by the then railways minister Nitish Kumar. It was to be completed by 2007 at a cost of Rs 84 crore,which has escalated to Rs 200 crore. Sources revealed that the main reason for the delay was that there were nearly 29 railway crossings on the 42 km track and the railways had to make arrangements for staff at each crossing.