Freight corridor work runs into land issues in last leg

The Dedicated Freight Corridor Corporation (DFCC) is looking for a workaround on that because linear projects such as the corridor do not require a green clearance.

mumbai-ahmedabad bullet train, centre budget resources bullet train, bullet train india projectDFCCIL is a special purpose vehicle set up under the administrative control of the Ministry of Railways.(Representational Image)
Written by: Avishek G Dastidar
3 min readNew DelhiJun 10, 2022 01:19 AM IST First published on: Jun 10, 2022 at 01:19 AM IST

Work on the last stretch of the Dedicated Freight Corridor’s Western arm has come to a halt over land-related issues in Maharashtra, a senior official said.

Encroachers — or “non-title-holders”, as they are officially termed — are not moving from tracts of land at several places along the 100-odd km stretch between Vaitarna near Palghar and New Jawaharlal Nehru Port Trust of the Western corridor.

Advertisement

The National Green Tribunal had recently given a ruling to the effect that any kind of earthwork would require a green clearance. The Dedicated Freight Corridor Corporation (DFCC) is looking for a workaround on that because linear projects such as the corridor do not require a green clearance.