Within 24 hours of the Union power ministry waiving transmission charges for states buying electricity from Adani Green and Azure Power, the YSRCP-led Andhra Pradesh government signed a deal with Central utility Solar Energy Corporation of India (SECI), which had awarded a total of 12 giga watt (GW) projects to these two companies.
This waiver of ISTS (inter state transmission system) charges is estimated to have resulted in savings of 80 paise per unit (Rs 1,360 crore a year), in a way incentivising the state to buy power from the two projects. ISTS charges are levied when power is wheeled from one state to another using the national grid.
The Power Ministry’s order on November 30, 2021, essentially eased two conditions stipulated in an earlier order issued just a week ago on November 23. These two conditions were: (i) that the project be commissioned before June 30, 2025, and (ii) that the power from the project be within the renewable power obligation (RPO) of the state. RPO requires states to buy a certain percentage of its total power from renewable sources.
The first 1,000 MW of Adani Green power is expected to be commissioned only in April 2025, with the balance beyond June 2025, said an Andhra government source.
When contacted, an Adani Green spokesperson said, “The ISTS waiver was embedded by SECI in the manufacturing-linked tender to put it on equal footing vis-a-vis other renewable energy tenders of the time… It is important to note that it is the DISCOM that benefits from the ISTS waiver, not the project developer, who only receives a fixed tariff.” The spokesperson also said that the reasons for delay in commissioning were beyond the scope of the developer.
Adani Group Chairperson Gautam Adani, his nephew Sagar Adani and six others were indicted by the US Department of Justice for paying or offering to pay $250 million bribes to bag lucrative power contracts from the state.
A day after the Power Ministry’s November 30, 2021, order, Andhra Pradesh signed a Power Sale Agreement (PSA) with SECI, the nodal agency in the country for renewable power, on December 1, 2021.
“If the charges had not been waived, it would have cost the state 80 paise over and above the Rs 2.49 per unit it agreed to pay for the power (since it had to be wheeled from Gujarat),” said an official in Andhra Pradesh government.
Since the state had agreed to purchase 1,700 crore units of power from SECI, the Power Ministry’s intervention waived Rs 1,360 crore for the government. As the PSA is for 25 years, the waiver would have translated to a cumulative amount of Rs 34,000 crore for this period.
“One of the conditions which Andhra Pradesh had put forward to buy power from SECI was that there should be no transmission charges. Once the transmission charges were waived in perpetuity, the government signed the agreement,” the Andhra Pradesh government official in the know said.
The new government headed by TDP’s N Chandrababu Naidu is currently scrutinising the PSA signed during the previous government under YSR Congress Party. This comes after the US court indictment of Gautam Adani, Sagar Adani and six others.
The indictment had alleged that Rs 1,750 crore out of Rs 2,029 crore in bribes went to a top-ranking Andhra Pradesh government official. These were termed as “baseless” and denied by the Adani Group,
On the delay in delivery of power, the Adani Green spokesperson said, “…The Scheduled completion date (SCOD) of renewable project under SECI PPAs is constrained by end-to-end Evacuation availability and readiness, which is planned and monitored by the Central Transmission Utility (CTUIL) and is beyond the scope and control of the developer. SECI or any other central nodal agency gives extensions in SCOD to account for these transmission delays, recognising that the project developers cannot evacuate power if the Central Transmission Unit (CTU) system is unavailable, which would leave the plants stranded.
Accordingly, due to delay in grid availability SECI has extended the SCOD dates for our project to match with the CTUIL provided timelines coordination-meeting. We are fully committed to supply energy under the PPAs from such a new SCOD timeline.”