Coal-fired plants’ inflexibility jeopardises India’s clean energy push: Can an incentive scheme work?

India operates a unified national grid connecting generators, distribution utilities, and bulk consumers. Any demand-supply imbalance affects system frequency

renewable energyWith the addition of over 44 GW of renewable energy in 2025, India’s total installed renewable energy (RE) capacity has reached 262 GW. (File)
Written by: Pratyush Deep
6 min readNew DelhiFeb 28, 2026 11:01 AM IST First published on: Feb 28, 2026 at 11:01 AM IST

Even as India rapidly expands its renewable energy capacity, the operational limitations of coal-fired power plants is emerging as a critical bottleneck in creating more headroom for clean energy in the national grid.

With the addition of over 44 GW of renewable energy in 2025, India’s total installed renewable energy (RE) capacity has reached 262 GW, accounting for more than 51% of the country’s overall installed power capacity.

Advertisement

But integrating this growing green energy into a grid is proving difficult. Addressing the issue, Ghanshyam Prasad, Chairperson of the Central Electricity Authority (CEA), said an incentive scheme is now being proposed to encourage thermal power plants to adopt greater operational flexibility.