Pune Infra watch: PMC floats fresh tenders for Sinhagad Road flyover project

The PMC has had technical hurdles in implementing the flyover project and had to thrice cancel the tender process.

Dandekar bridge on Sinhagad road in Pune. (Express Photo: Arul Horizon)Dandekar bridge on Sinhagad road in Pune. (Express Photo: Arul Horizon)
Written by: Ajay Jadhav
5 min readPuneMay 21, 2021 12:13 PM IST First published on: May 20, 2021 at 01:17 PM IST

The Pune Municipal Corporation (PMC) has for the fourth time floated tenders for a flyover project, from Rajaram bridge to Funtime theatre, to end traffic woes on Sinhagad Road. The estimated cost of the project is Rs 135 crore. Ahead of that, it took the opinion of the Pune metro rail to ensure that it will not face any problem in the proposed elevated metro rail route on the stretch.

The PMC has had technical hurdles in implementing the flyover project and had to thrice cancel the tender process.

Advertisement

The civic administration first started the tender process for the project in September 2019 with an estimated cost of Rs 117 crore but it was cancelled as the bidder quoted 18 per cent above the project cost. It was again cancelled in the second attempt in February last year as only two bidders participated in the bidding. Thereafter, the tender process was started in March last year, but had to be cancelled on the request of contractors who were unable to participate owing to the lockdown.