Three missing links: Can Metro Line 6 still meet its 2027 deadline?

With 88% of construction complete, unresolved land disputes at Shyam Nagar, Kanjurmarg junction and the proposed depot remain the biggest hurdles for Mumbai's east-west metro corridor.

metro line 6While about 1,000 sqm is required for the station building, another 350 sqm is needed across the road for an entry-exit point. (Express Photo by Akash Patil)
Written by: Sabah Virani
4 min readMumbaiJun 21, 2026 12:13 PM IST First published on: Jun 21, 2026 at 12:13 PM IST

Mumbai’s Metro Line 6 corridor may be nearing completion, but three unresolved land acquisition disputes continue to cast a shadow over its planned 2027 opening.

The 15.3-km east-west metro line connecting Swami Samarth Nagar in Jogeshwari to Vikhroli has achieved 88 per cent physical progress. Yet critical work remains stalled at three locations the proposed Shyam Nagar station in Jogeshwari, a missing viaduct section at the Jogeshwari-Vikhroli Link Road (JVLR)-Eastern Express Highway (EEH) junction in Kanjurmarg, and the Metro Line 6 depot at Kanjurmarg.

Advertisement

According to officials from the Mumbai Metropolitan Region Development Authority (MMRDA), land acquisition efforts at all three locations have been ongoing for at least three years.

Sabah Virani is a journalist with The Indian Express’ Mumbai bureau, covering infrastructure, housin... Read More