This is an archive article published on July 8, 2014

SC raps Campa Cola residents for agitation, BMC for demolition bid

Counsel for residents argues for fresh hearing in view of new facts, court fixes July 21 as date

3 min readMumbaiJul 8, 2014 12:15 AM IST First published on: Jul 8, 2014 at 12:15 AM IST

The Brihanmumbai Municipal Corporation (BMC) told the Supreme Court Monday that all possibilities of an “out-of-court” settlement had been exhausted over the proposed demolition of 96 flats built illegally in Wolri’s Campa Cola compound.

A bench led by Justice S J Mukhopadhaya had asked the BMC’s counsel if there was a scope for a settlement without involving the court in view of the longstanding dispute and the nature of the case.

Advertisement

The civic body’s counsel responded, “An out-of-court settlement was just not possible anymore.”

The bench, however, also questioned the BMC taking pretext of the court order to forcibly evict residents of the illegally constructed flats and proceed with the demolition. The bench categorically said it was the BMC, and not the court, which had adjudicated upon the legality of the construction of these flats and hence the municipal body should not give an impression as if the court had held these houses to be illegal.

Latest Comment
Post Comment