India’s most ambitious urban renewal project has hit a snag

Five of seven statutory clearances are still pending; the Hyderabad-based contracted company said it had been informed late about key approvals, while a Mumbai civic body official said scrapping tenders now would only create more delays

The Deonar landfill as seen from Maharashtra Nagar, Mankhurd.The Deonar landfill as seen from Maharashtra Nagar, Mankhurd (Express Photo by Amit Chakravarty).
Written by: Pratip Acharya
6 min readMumbaiAug 13, 2026 08:21 PM IST First published on: Aug 12, 2026 at 04:08 AM IST

A showpiece Maharashtra government project to relocate a section of residents of Dharavi in Deonar – the site of the largest and oldest landfill in Mumbai – is stuck in a maze of red tape. Work has yet to begin on clearing a portion of the 99-year-old landfill – marking a delay of over six months from the original deadline – Right to Information (RTI) records obtained and investigated by The Indian Express show.

The records show the Brihanmumbai Municipal Corporation (BMC) awarded a Rs 2,537-crore contract to clean up the landfill to Hyderabad-based Navayuga Engineering Company Limited (NECL). January 2026 was the deadline for all approvals to be obtained and work to begin, but five of the seven statutory clearances are still pending.

Pratip Acharya is a seasoned journalist based in Mumbai reporting for The Indian Express Read More