Mumbai-Pune expressway’s ‘missing link’ to bridge the two cities closer

Once the ‘missing link’ — comprising a cable-stayed bridge, a viaduct and two tunnels, which will cut distance and travel time — is ready, motorists will be able to bypass the ghats, without worrying about falling boulders during the monsoon.

mumbai pune expressway, Mumbai-Pune Expressway, MSRDC, MSRDC Projects, Maharashtra State Road Development Corporation, Mumbai news, Maharashtra, Indian Express, current affairsWith the ‘missing link’, the MSRDC also aims to solve an annual worry during the monsoon — traffic gridlocks due to falling boulders.
Written by: Sweety Adimulam
6 min readMumbaiJul 23, 2023 03:40 PM IST First published on: Jul 17, 2023 at 04:11 AM IST

Even as the monsoon is playing hindrance, engineers at Maharashtra State Road Development Corporation (MSRDC) are hopeful of completing the challenging ‘missing link’ project on the Mumbai-Pune expressway by December 2023 or early 2024.

Having completed 34 per cent work on the 640-metre-long cable-stayed bridge — the most challenging part of the project — the engineers, working at a height of 100 metres above the Tiger Valley in Lonavala-Khandala region, say the 13-km-long project is set to achieve a major milestone this month when another key part — the viaduct — will undergo its first load testing on the Pune-bound corridor.

Advertisement

The monsoon has posed the biggest challenge to engineers working on the cable-stayed bridge with heavy rain, which occurs almost daily, hampering work. This portion falls in the ghat section, which sees 50- to 65-mm rain daily, even more, during the monsoon.