Changing City: Work on Andheri East subway gains speed, expected to be ready by April 2024

The Parsi Panchayat Andheri East Subway could potentially resolve traffic woes of the area

andheri east subwayConstruction underway at Andheri East. (Express)
Written by: Sweety Adimulam
1 min readMumbaiJan 8, 2024 05:36 PM IST First published on: Jan 5, 2024 at 03:05 PM IST

After missing two deadlines, the Parsi Panchayat Andheri East Subway work is progressing with speed.

While the work was slowed down previously due to the Covid-19-induced lockdowns, there were also challenges in taking up the work at Western Express Highway (WEH) since the highway sees heavy traffic throughout the day and it was difficult to obtain permission.

Advertisement
Parsi Panchayat Andheri East Details of the Parsi Panchayat Andheri East subway.

Further, work on Metro Line 7 (Andheri E to Dahisar E) was ongoing then. Simultaneous subway construction work would have added to the traffic congestion in this scenario.

Now, the Metro work is complete on WEH, and the Mumbai Metropolitan Region Development Authority (MMRDA) has begun to focus on the subway work. It is expected to be ready by April 2024.