Premium

After fatal Mulund collapse, MMRDA orders corridor wide safety audit of Metro Line 4

Authority cites contractor negligence and lack of supervision in preliminary findings; inspection from Wadala to Thane to cover every structural element, unsafe work may be halted

One Dead, Three Injured as Cement Metro Pillar Collapses on Rickshaw in Mumbai’s MulundA view of a broken part of the metro pillar after a portion of it collapsed during the construction work, at LBS Road, Mulund, in Mumbai. (Source: ANI)

A day after a parapet wall segment from the under construction Metro Line 4 collapsed onto LBS Road in Mulund, killing one person and injuring three others, the Mumbai Metropolitan Region Development Authority MMRDA has ordered a special intensive safety inspection of the entire corridor and blamed preliminary lapses on the contractor and supervising consultant.

In a statement submitted to the deputy commissioner of police, Zone 7, Mulund West on Sunday, the authority said, “As per preliminary assessment, the incident appears to have occurred due to negligence on the part of the contractor sub-contractor concerned and lack of adequate supervision by the general consultant of Metro line 4. However, a detailed investigation is being initiated to ascertain the exact cause and fix responsibility.”

The stretch where the incident occurred is being executed by a joint venture of Reliance Infrastructure and Astaldi SPA, with Milan Road Buildtech LLP as the subcontractor.

The parapet segment fell near pier P196, between Sonapur and Mulund Fire Station Metro stations. The line is scheduled to open in phases later this year.

In response, Additional Metropolitan Commissioner Ashwin Mudgal has ordered a corridor wide inspection from Wadala to Kasarvadavali in Thane, covering what officials described as “every nook and corner” of the project. The inspection will continue for three to four days and will include physical checks, documentation and identification of unsafe elements.

If any potential risk is identified, the inspection team has been authorised to suspend construction activity. Immediate rectification or removal of any unsafe element has been mandated, along with submission of daily reports detailing observations, corrective steps and preventive measures.

The scope of inspection includes parapets, beams, crash barriers, structural elements above live traffic, public access areas, temporary supports, construction debris, barricading and compliance with approved drawings and safety protocols.

Story continues below this ad

Three senior MMRDA officials are leading the exercise. Basavraj Bhadragond, director projects, is heading both the inspection and the investigation committee. Abhijit Bhishikar is overseeing the section from Wadala to Sonapur, while Madhukar Kharat is in charge of the stretch from Sonapur to Gaimukh.

Members of the general consultant consortium, which includes DB Engineering and Consulting, Hill International Inc and Louis Berger Consulting Private Limited, are also part of the inspection team. The consortium was fined Rs 1 crore by the MMRDA following the incident.

Notably, two officials from the consortium, project consultant Sai Suresh and project manager Avdhut Inamdar, have been named as accused in the FIR.

The inspection team also includes package executive engineers, quality assurance and design proof checking officials, safety engineers and two external members from Metro Line 9 and Line 5 who will submit independent findings.

Story continues below this ad

Earlier this month, what appeared to be a crack near pier P189 in Mulund was flagged on social media. The MMRDA had clarified that it was residue from foam sheets used temporarily during construction.

“MMRDA follows a robust approval process for Metro construction, involving nearly 1,200 approvals. In addition, all projects require statutory clearances from bodies such as the Research Designs and Standards Organisation RDSO, the Independent Safety Assessor ISA, and the commissioner of Metro Rail Safety CMRS, which are reviewed and renewed periodically,” the authority had said in a statement.

Sabah Virani is a journalist with The Indian Express’ Mumbai bureau, covering infrastructure, housing and urban issues. In the realms of technical fields, she brings out human stories and the pace of change ongoing in the city. Expertise Specialised Role: Tracking infrastructure in Mumbai and the wider Mumbai Metropolitan Region (MMR), Sabah’s reporting tracks progress on various projects. From bridges to metros, she mixes technical details with resourceful information. Core coverage areas: Sabah keeps a close eye on the activities of the Mumbai Metropolitan Region Development Authority (MMRDA) and its projects across the MMR, including the metros, road projects, bridges, the bullet train, pod taxi, its role as a planning authority, and more. She also watches for developments from the Maharashtra State Road Development Corporation (MSRDC), City and Industrial Development Corporation of Maharashtra (CIDCO) and the GoM’s Urban Development department. Housing: Sabah also tracks developments in housing, particularly the workings of the Slum Rehabilitation Authority (SRA). She also keeps a keen watch on the big redevelopment projects ongoing in Mumbai, including the Dharavi Redevelopment Project, Motilal Nagar, Kamathipura, BDD Chawl redevelopment, among others. Occasionally, she reports on the environment, biodiversity, waste, arts and culture. Experience: Prior to working for the Indian Express, Sabah covered the municipality, civic issues and miscellaneous for Hindustan Times. Before that, she covered all things Mumbai for the online publication Citizen Matters. She has also worked as an editorial assistant at FiftyTwo.in.   ... Read More

Stay updated with the latest - Click here to follow us on Instagram

Advertisement
Loading Recommendations...
Latest Comment
Post Comment
Read Comments