Premium

Metro Line 4 after Mulund accident: Decision on retaining consultant ‘taken in larger public interest’, says MMRDA

‘Line nearly 80% complete, new consultant would take months to catch up'.

In February, in a tragic incident in Mumbai, one person was killed and three others were injured after a portion of the parapet wall of the under-construction Mumbai Metro Line 4 collapsed on Lal Bahadur Shastri (LBS) Road in Mulund. (Express Photo by Deepak Joshi)In February, in a tragic incident in Mumbai, one person was killed and three others were injured after a portion of the parapet wall of the under-construction Mumbai Metro Line 4 collapsed on Lal Bahadur Shastri (LBS) Road in Mulund. (Express Photo by Deepak Joshi)

Citing nearly 80 per cent completion of work on Metro Line 4 and the risk of delay if a new consultant were appointed, the Mumbai Metropolitan Region Development Authority (MMRDA) on Tuesday justified its decision to retain the general consultant it had threatened to sack following the fatal Mulund slab collapse, calling it a move taken “strictly in the larger public interest”.

The clarification came a day after The Indian Express reported about MMRDA going back on its earlier stance and deciding to continue with DB Hill–LBG consortium as the general consultant (of GC) for Metro Line 4. The agency had earlier announced its intention to terminate the contract in the aftermath of the February 14 incident in Mulund, when a parapet slab fell onto LBS Road, killing one person and injuring three others.

“Given that the project has already achieved nearly 80% physical progress, and that appointing a new general consultant at this stage would require approximately 3–4 months, potentially delaying the project and impacting public convenience, a considered decision has been taken to allow the existing GC to continue — strictly in the larger public interest and subject to stringent, non-negotiable conditions,” MMRDA said in a statement to this newspaper.

The authority also sought to draw a distinction between institutional failure and an on-site error. Claiming termination proceedings had been initiated against the consultant, MMRDA said its detailed inquiry found the incident “not attributable to any systemic failure in design or supervision by the GC, but was linked to an execution-level lapse at site, specifically a welder’s error”, and therefore found “no direct institutional culpability of the GC”.

The slab collapse was triggered after connections securing a parapet wall to the viaduct were accidentally cut by a welder the night before. In the 11 hours that followed, neither the consultant nor MMRDA engineers intervened before the slab fell onto LBS Road. Ramdhani Yadav, 50, who was travelling in a rickshaw, was killed. His relatives Rajkumar Indrajeet Yadav, 45, and Mahendra Pratap Yadav, 52, were critically injured and spent over two months in hospital before being discharged. A fourth person, Deepa Rula, 40, was discharged shortly after the incident. The injured have not yet received any compensation beyond hospital bills and rent paid by the sub-contractor.

In its report to the Bombay High Court, MMRDA put primary blame on the contractor, citing “procedural non-compliance by RAJV and insufficient site supervision by the General Consultant”. Its own engineers were also flagged for inadequate site visits.

Conditions apply

MMRDA further said that the decision to retain the consultant comes with stringent conditions, including a complete replacement of the general consultant’s team, mandatory joint pre-inspection before all critical activities, dedicated supervision during critical works, a permit-to-remove system for all dismantling works, prohibition of verbal instructions, mandatory toolbox talks on safety procedures, and strict adherence to standard operating procedures, especially when working at heights and in live traffic, and a zero-tolerance clause, which would trigger immediate termination in case of any future lapse.

Story continues below this ad

“MMRDA reiterates that there has been no dilution of its zero-tolerance stance on safety. The decision reflects a calibrated approach — ensuring accountability through penalties and corrective measures, while also safeguarding the timely completion of a critical public infrastructure project,” the authority said in its statement.

Sabah Virani is a journalist with The Indian Express’ Mumbai bureau, covering infrastructure, housing and urban issues. In the realms of technical fields, she brings out human stories and the pace of change ongoing in the city. Expertise Specialised Role: Tracking infrastructure in Mumbai and the wider Mumbai Metropolitan Region (MMR), Sabah’s reporting tracks progress on various projects. From bridges to metros, she mixes technical details with resourceful information. Core coverage areas: Sabah keeps a close eye on the activities of the Mumbai Metropolitan Region Development Authority (MMRDA) and its projects across the MMR, including the metros, road projects, bridges, the bullet train, pod taxi, its role as a planning authority, and more. She also watches for developments from the Maharashtra State Road Development Corporation (MSRDC), City and Industrial Development Corporation of Maharashtra (CIDCO) and the GoM’s Urban Development department. Housing: Sabah also tracks developments in housing, particularly the workings of the Slum Rehabilitation Authority (SRA). She also keeps a keen watch on the big redevelopment projects ongoing in Mumbai, including the Dharavi Redevelopment Project, Motilal Nagar, Kamathipura, BDD Chawl redevelopment, among others. Occasionally, she reports on the environment, biodiversity, waste, arts and culture. Experience: Prior to working for the Indian Express, Sabah covered the municipality, civic issues and miscellaneous for Hindustan Times. Before that, she covered all things Mumbai for the online publication Citizen Matters. She has also worked as an editorial assistant at FiftyTwo.in.   ... Read More

Stay updated with the latest - Click here to follow us on Instagram

Advertisement
Loading Recommendations...
Advertisement
Latest Comment
Post Comment
Read Comments