MahaRERA asks L&T Realty subsidiary to compensate homebuyer

The regulatory body has directed L&T Parel Project LLP to pay interest on the buyer’s investment for five months.

THE MAHARASHTRA Real Estate Regulatory Authority (RERA) has directed L&T Parel Project LLP — a subsidiary of L&T Realty — to compensate a woman who bought a flat in a south Mumbai project. The regulatory body has directed L&T Parel Project LLP to pay interest on the buyer’s investment for five months.

The woman had booked a flat in the T-4 wing of Crescent Bay project in Parel and was expecting possession by September 30, 2017, with a grace period of six months. She claimed that the respondents, L&T Parel Project LLP and Omkar Realtors, failed to hand over possession of the flat on the agreed date.

In an order dated September 4, the regulatory body noted that the respondents issued a possession letter to the complainant on March 29, 2018, asking her to take possession and clear dues amounting to Rs 15.96 lakh.

The woman, however, refused to take possession on the grounds that the clubhouse was not operational. She also claimed that the water connection was pending. The respondents claimed that they had applied for a permanent water connection but work had been delayed because road-cutting work was underway.

Subscriber Only Stories
UPSC Key-September 27, 2022: Why you should read ‘Mankading’ or ‘Rarest o...Premium
Why India has lashed out at the US over its F-16 package to PakistanPremium
Kurmi club: On national path, Nitish looks east, at UP’s Sonelal Pa...Premium
Interview: MD-CEO, Central bank of India | ‘During PCA years, none of our...Premium

After considering the arguments, the regulatory body ruled that respondents had failed to deliver the possession on the agreed date and the complainant was entitled to get interest on her investment. “The complainant has desire to continue in the project and therefore, she is entitled to get interest on the prescribed rate, which is 2 per cent above SBI’s highest MCLR from April 1, 2018, till she gets possession of the flat,” said RERA member B D Kapadnis, who was hearing the matter.

“The respondents shall pay the complainant interest on her investment, i.e., the consideration amount Rs 4,03,87,720 and TDS amount from April 1, 2018 to August 31, 2018. The complainant shall either deposit or shall pay the balance of clubhouse Rs2,00,000 on completion of it, till then she shall not use the clubhouse. On completion of the clubhouse Rs 4,00,000 deposited by the complainant be paid to the respondents,” read the order.

When contacted, the spokesperson for L&T Realty did not comment on the matter. Omkar Realtors said they handled only the SRA part of the project and did not comment on the matter.

First published on: 13-09-2018 at 04:58:31 am
Next Story

Citing union pressure, Coal rolls back, puts on hold plan to let private firms mine for sale

Latest Comment
Post Comment
Read Comments
Advertisement
Advertisement
Advertisement
Advertisement