3 min readMumbaiJul 4, 2026 10:53 AM IST
First published on: Jul 4, 2026 at 10:53 AM IST
As work on the Mumbai Metropolitan Region Development Authority’s (MMRDA) pod taxi project gathers pace, around 174 families will have to be rehabilitated to make way for terminal stations and related infrastructure at Bandra and Kurla.
A ground survey carried out by the MMRDA has identified 128 structures, mostly slum homes, on a plot next to Bandra railway station where the Bandra terminal is proposed. Five of these are commercial establishments.
In Kurla, 46 structures, including chawls and slum homes, have been identified along the stretch between Kurla railway station and the police housing colony, where the terminal station and a skywalk connecting it to the station will come up. Officials said a few more structures could be affected if space is required for an escalator, though the survey is still being finalised.
A joint verification of the survey is currently being carried out by the MMRDA’s transport, survey and social development departments.
“Once the verification is completed, an annexure of the affected structures will be prepared. After rehabilitation tenements are identified, allotment will be done through a lottery,” an MMRDA official said.
Officials said all structures that existed when the baseline survey was conducted will be eligible for rehabilitation under the Mumbai Urban Transport Project II, under which the pod taxi project is being implemented. Eligible families will receive 269 sq ft rehabilitation tenements. While MMRDA is exploring options in the western suburbs following requests from residents, some families are likely to be rehabilitated in Kurla.
Even as construction has begun at a few locations, land acquisition for the two terminal stations is still underway.
At Bandra, the terminal will come up on a 4,000 sq m plot belonging to the Rail Land Development Authority beside the railway station. Though in principle approval for the land transfer was granted in March, the agreement is yet to be signed.
At Kurla, the terminal is planned on the existing police housing colony near Bhabha Hospital. The proposal involves redeveloping the site, with the station on the lower floors and new police housing above it. While the police department has agreed to the plan, the government is yet to issue the required resolution.
The first phase of the project, comprising 3.36 km and eight stations, is expected to be completed by the end of 2028. Initially, the Bandra and Kurla sections will operate independently before being connected as part of the full 8.85 km network across Bandra Kurla Complex.