The National Green Tribunal (NGT) on Wednesday directed the Uttar Pradesh Chief Secretary, to disclose the steps to be taken for making the non-functional sewage treatment plants (STPs) functional and for ensuring that all the STPs comply with specified norms within four weeks.
The bench, comprising Justice Prakash Shrivastava, Justice Sudhir Aggarwal and expert member Dr A Senthil Vel emphasized the need for immediate action to address the critical sewage management issues in multiple districts of Uttar Pradesh along the course of Ganga river and its tributaries.
The NGT’s intervention comes in the wake of a compliance report filed by the Uttar Pradesh Government on October 30, detailing the current status of sewage treatment and the discharge of untreated wastewater into the river. The report highlighted alarming gaps in sewage treatment infrastructure, especially in key districts of Prayagraj, Kanpur Dehat and Ayodhya.
“On examination of the status of district Prayagraj, we find that within the Prayagraj Nagar Nigam, 468.28 MLD sewage is generated, the quantity of sewage treated is 394.48 MLD and the existing treatment 2 capacity of STPs is only 340 MLD. Therefore, the gap in sewage generation and existing capacity is 128.28 MLD. The report further reflects that in Prayagraj, untreated sewage from 25 untapped drains is discharged into river Ganga and from 15 untapped drains in river Yamuna,” read the order.
The NGT, in its order, also said that there is neither a single sewage treatment plant constructed in Kanpur Dehat district nor a sewage treatment facility. “So far as Ayodhya is concerned, we find that the position is somewhat similar. Conditions in respect of other districts is not better,” said the tribunal.
The Central Pollution Control Board (CPCB) report, presented before the tribunal, disclosed that out of 326 drains identified in the state, 247 are untapped, contributing to the discharge of a massive 3513.16 MLD of untreated sewage into the Ganga and its tributaries.
The CPCB also pointed out that out of the 41 STPs located across 16 towns along the Ganga, six are non-operational, and 34 out of 35 operational STPs do not comply with environmental norms, particularly concerning faecal coliform levels.
“The state must disclose the timeline for tapping these drains and for setting up the STPs for treating the sewage from these drains. Hence, we require the Chief Secretary, State of UP to file the affidavit disclosing the information relating to each of the drains in different districts, sewage generated from it, the STP to which it is proposed to be connected, the timeline for making the STP functional, funds which are available, identification and allotment of land for setting up the STP,” directed the three-member board.
The NGT has scheduled the next hearing for January 20, 2025.